Precedence network type uses arrows

Assignment Help Project Management
Reference no: EM133285556

Question 1. This (often secondary) precedence network type uses arrows or arcs to visually represent tasks and nodes to visually represent events or milestones.

A. precedence diagram

B. activity on arc (AOA)

C. nodes and arrows graphic

Question 2. A ______ relationship dictates that a task must start before the successor can finish.

A. start-to-finish (SF)

B. start-to-start (SS)

C. finish-to-finish (FF)

Question 3. Some of the costs in the ______ category include overhead, indirect costs, and costs related to the time value of money.

A. resource or direct costs

B. time-dependent costs

C. incentive payments

Reference no: EM133285556

Questions Cloud

Value of virtual signage to potential advertisers : Which of the following best supports the value of virtual signage to potential advertisers?
Performing cost benefit analysis : A property manager is performing a cost benefit analysis concerning a change that she's considering for the clients property
Patience is virtuous by proxy : Why do you think that patient people are more likely to exude other tendencies that are considered virtuous, thus patience is virtuous by proxy.
Healthcare division into separate entity : In the calendar year 2016, Philips spun-off its healthcare division into a separate entity.
Precedence network type uses arrows : This (often secondary) precedence network type uses arrows or arcs to visually represent tasks and nodes to visually represent events or milestones.
Determining funding equity in schools : What are some issues when determining funding equity in schools? What factors in your state or area determine your school's funding?
Conducting marathon for hurricane fiona : Our project will be on raising funds by conducting a marathon for hurricane Fiona in nova scotia.
Main phases of the project life cycle : Who could be the potential stakeholders 50th anniversary? Typically, what is the main phases of the project life cycle?
Successful implementation of project : The successful implementation of a project is highly dependent on project control, and therefore on the practice of informing, monitoring and analysing.

Reviews

Write a Review

Project Management Questions & Answers

  BSBPMG412 Apply project cost management techniques

BSBPMG412 Apply project cost management techniques Assignment Help and Solution, Sydney Metro College - Assessment Writing Service

  Hr manager and characteristicsdo you want to be an hr

hr manager and characteristicsdo you want to be an hr manager? create a list of characteristics and skills that a

  Project procurement management plan

Find a project procurement management plan example or template. If you happen to find a template online

  Highlighting additional study and preparation

If applying for a PMI certification, what kind of action plan can be done with timeline, highlighting additional study and preparation

  Question about aggregate production planningwork thru this

question about aggregate production planningwork thru this to compare chase versus level aggregate plansas a manager of

  Team project sky wrench maintenance hanger relocation

Team Project Sky Wrench Maintenance Hanger Relocation, You are in the maintenance office of a medium sized repair facility. The senior manager has tasked you to come up with a project plan and budget to move your 51-person maintenance facility from h..

  Sustainable development efforts

How can you get others involved so that they too take part in some of these sustainable development efforts? What is the way motivate people to be part.

  What is required to prove promissory estoppel

List the four types of consideration described in the text.-  What is required to prove promissory estoppel when consideration is missing?

  Write on a Reflective Report on leadership

Write on a Reflective Report on leadership - Describe how the leadership concept is implemented in your work environment

  Why is it important to include a business resilience program

Why is it important to include a Business Resilience program in your organization's ERM program?

  Evaluate the use of typography in editorial design

Y/601/6315-Editorial Design -BH027165 – Edexcel BTEC Levels 4 and 5 Higher Nationals specification in Art and Design-Analyse conventions of editorial layouts.

  Name five methods for organizing report data

Name five methods for organizing report data. Be prepared to discuss each. What three devices can report writers use to prevent readers from getting lost in the text?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd