Project Status Report (time based)

Project reporting is the act of collecting and distributing project information. Project information is distributed to many groups of stakeholders and should be adapted to provide information at an appropriate level, format, and detail for each type of stakeholder

2 GANTT CHART WITH BUDGETED COST
This chart represents the original baseline plan for the project.

3 ACTUAL PERFORMANCE
This chart represents the work performed with the actual cost incurred. The data date is the end of week 8.
4 VARIANCE ANALYSIS
Complete the table below. Calculate the values at the data date and show the formula used.
Describe the current status of the project in terms of time and cost performance.

5 FORECASTS- VALUES AT COMPLETION
Calculate the following forecast values and motivate your choice of the EAC formula used
6 FORECAST COMPLETION DATE
Even though a more accurate forecast completion date is derived from the updated schedule, the forecast duration could also be derived from the Schedule Performance Index (SPI) and can help forecasts the end date of the project (see AS 4817-2006 pp.13-15 Section 2.3.2).

Calculate the forecast project duration using the SPI of the project at the data date.

7 MILESTONE REPORT
8 ISSUES, RISKS AND OTHER MATTERS
Include any other matters for reporting such as issues, risks and any other relevant matters and their potential impact on the project in the future, that need to be brought to the attention of the stakeholders.

9 LEARNING FROM THIS EXERCISE
Describe in your own words what you have learned from this exercise. E.g. would comparing the budget with actual cost alone have given an accurate picture of the project?

Assessment 1 Part B
Exception Report (event based)

1. PROJECT INFORMATION
2. ESTABLISH THE NEED FOR AN EXCEPTION REPORT
3. EXCEPTION REPORT
4 LEARNING FROM THIS EXERCISE

Question 1 What are the differences between a time-based report and an events-based report?
Question 2 What are the advantages and disadvantages of an events-based report for the project?
Question 3 What are the advantages and disadvantages of an events-based report for the project manager and the project management team?

Attachment:- Assessment - Project Status and Exception Report exercise and template.rar

Reference no: EM132494671

Questions Cloud

Computing accrual and cash income : Compute the company's first-year net income under both the cash basis and the accrual basis of accounting. Computing accrual and cash income
Accurate future projections concerning interest rates : As the financial manager in developing forecast for the firm, where would you go to in order to start your forecast and refine it with more accurate future proj
What incentive conflict was controlled by loyalty payments : What incentive conflict was being controlled by these loyalty payments? What advice did Intel ignore when they adopted this practice?
What do expect the price of these bonds to be one year : If interest rates remain unchanged, what do you expect the price of these bonds to be one year from now? In three years? In eight years? In 12 years? In 13 year
PPMP20010 Executing and Closing Projects Assignment : PPMP20010 Executing and Closing Projects Assignment help and solution, Central Queensland University - assessment writing service - Calculate the values
When construct the replicating portfolio for the option : Compute the value of a European call option on the stock with strike K=102 K=102. The stock does not pay dividends. Consider a1 1-period binomial model
How much will they need to save : How much will they need to save each month to reach their goal (17 months from now), if they start today?
Find what is the ending inventory : Find What is the ending inventory? A Company ships merchandise in a consignment arrangement. The arrangement specifies a 20% commission.
What is the new stock price : The Rivoli Company has no debt outstanding, and its financial position is given by the following data:

Reviews

Write a Review

Project Management Questions & Answers

  What is your ethical responsibility

You're inclined to slump in your chair, slam your notebook down on the table, and stop taking notes. - What is your ethical responsibility? - What nonverbal message should you send?

  What is the purpose of the project charter

What is the purpose of the project charter? Discuss the advantages that you will have as you work on your own project by developing this charter early in the project.

  Considering various business risks

I work for an Education Organizational Development and Learning department for a leading not-for-profit health care system.

  Explain what action you would recommend to shawn husband

After reviewing the Project Management Institute's (PMI) Code of Conduct, specify which potential violation exists. As the team leader, describe how you expect Shawn to proceed regarding this issue. Explain what action you would recommend to Shawn's ..

  Did the employer have a right to terminate cook for failure

Was Cook precluded from bringing a wrongful discharge case on her own rather than seeking a remedy under the polygraph statute?

  Why is there no market failure in the first situation

Why is there no market failure in the first situation involving the Smiths and the Browns? Why may there be market failure in the situation with several families?

  What was the most the dutch company could lose

What was the most the Dutch company could lose on its French franc receivable, assuming that France and the Netherlands stuck to the ERM with a 15% band on either side of their central cross rate?

  When is a project manager needed for a project

When is a project manager needed for a project? What is the criteria for when a project manager is needed? Is it based simply upon the cost of a project?

  What are the implications of the article for management

What was the topic of this article? Based upon the article what do we know about the topic of the article - What is your over all evaluation of the articles

  Project has an initial cost

A project has an initial cost of $52,450, expected net cash inflows of $10,000 per year for 7 years, and a cost of capital of 12%. What is the project's MIRR?

  Justification and construction of short and long-term goals

Reflect on their learning and critically evaluate their learning experiences and consider how they will apply those experiences to other modules on their programme of study and their future career aspirations.

  What is the new economic order quantity

What is the new economic order quantity? - How many orders will now be placed?  -  What is the total annual cost of managing the inventory with this policy?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd