Reference no: EM132592826
PMAN639 Project Quality Management - University of Maryland Global Campus
A. Please answer the following True or False questions
1) Affinity diagram is used to identify the root causes of a problem.
True ______ False _______
2) A process is capable if the variations fall within +- 3 standard deviation
True ______ False______
3) Random variationsfall outside the control limits.
True ______ False______
4) Control charts tell Project Managers how to control the project.
True ______ False______
5) nP chart is used when the number of defects per unit is fixed at n
True ______ False______
6) A process in control may produce unacceptable output.
True ______ False______
7) A Six Sigma process must have a process capability index of 6.
True _____ False________
8) For a Normally distributed process the control limits are + - 3 times the standard deviation
True _____ False________
9) Both X bar chart and R chart must be out of control for the process to be out of control
True _____ False________
10) Run chart can be used as a measurement tool to track changes in a process over time.
True _____ False________
B. Please answer the following multiple choice questions:
1. Which of the following tools are used to get the shape of the distribution.
A) Matrix diagram
B) Histogram
C)Affinity Diagram
D) Check sheets
E) Process map
2. Which of the following tools are used to find the relationship between two variables?
A) Process Map
B) Fishbone diagram
C) Pareto Chart
D) Scatter plot
E) Control chart
3. Which of the following is true of special cause variation?
A) It is uncontrollable.
B) It is centered around the mean.
C) It is inherent in the process.
D) All of the above.
E) None of the above
4. A true 3 Sigma Process should not have more than _______defects per million opportunities
A. 6,210
B. 3.4
C. 2700
D. 45500
5. An R chart is used to monitor __________.
A. Variation of the Mean
B. Process Dispersion
C. Trend in mean value
D. Trend in standard deviation
C. Please respond to the following questions. Each question is worth 10 points:
1) 97.
1) Please create a process map for withdrawing cash from an ATM machine as described below:
Janet needed some cash and walks up to an ATM machine. She inserts her debit card. The machine returns the card and the monitor reads: "could not read the card try again". Janet recognizes that she has entered the card in the wrong direction. She takes the card and turns it around and insert the card again. The machine keeps the card and the monitor reads: "enter pass code". Janet enters a 4 digit code. The monitor reads: " error, try again".
Janet enters the code again. The monitor displays: Withdrawal? Yes No
Janet selects Yes. Displays shows:
" $100, $200, $300, $400, $______".
Janet selects $200. The machine pushes out 10 $20 bills. Monitor then displays "Receipt? Yes No". Janet selects No. Monitor displays "Take your cash" .
The machine returns the card. Display changes to "Thank You".
Janet takes the cash and her card and walks away.
.
2)
2) A customer relationship manager decided to track customer complaints as part of his ongoing customer satisfaction improvement program. After collecting data for two months, their check sheet appears as follows:
Type of Problem
|
Frequency
(number of times)
|
Call went to voice mail
|
8
|
Items damaged when received
|
21
|
Literature not in the box
|
9
|
Parts missing
|
13
|
Unit not working
|
2
|
Delivery was late
|
3
|
Construct a Pareto chart including the cumulative % frequency.What is the cumulative percentage of the two leftmost bars?
3) A project manager at Global Design Corporation has collected the following data on the size of software programs and the length of programming time. The company is bidding on a new system that is estimated to consist of 250,000 lines of code. Use the data to find the correlation function of coding time to the program size and estimate the number of days it would take to code the system.
Module
|
Size in 1000 lines of code (KLOC)
|
Number of days to code
|
1
|
160
|
68
|
2
|
158
|
66
|
3
|
148
|
70
|
4
|
135
|
59
|
5
|
178
|
72
|
6
|
170
|
68
|
7
|
158
|
64
|
8
|
138
|
65
|
9
|
200
|
70
|
10
|
195
|
68
|
11
|
189
|
65
|
12
|
173
|
68
|
13
|
159
|
70
|
14
|
163
|
71
|
15
|
150
|
66
|
16
|
140
|
65
|
17
|
206
|
73
|
18
|
144
|
64
|
19
|
157
|
70
|
20
|
183
|
74
|
21
|
195
|
75
|
22
|
190
|
77
|
23
|
182
|
69
|
24
|
152
|
65
|
25
|
174
|
69
|
4) A Black Belt consultant in the ABC Corporation reported the Sigma Performance of a manufacturing line as 3.1. Using Z score table calculate the % defective units coming off the production line.
5. Describe the Sources of Team Conflict
6) A project manager has developed the following data on a project tasks and duration. Please create an AON diagram, identify the critical path and the expected project duration. The customer has asked for a 95% confidence on the project completion date. Calculate the number of additional weeks the project manager needs to make that commitment.
|
|
Time estimation in weeks
|
Task
|
Predecessor
|
optimistic
|
Most likely
|
Pessimistic
|
A
|
|
3
|
4
|
5
|
B
|
A
|
1
|
8
|
15
|
C
|
A
|
2
|
4
|
6
|
D
|
A
|
4
|
8
|
12
|
E
|
B
|
7
|
9
|
11
|
F
|
C,B
|
2
|
5
|
8
|
G
|
E,D
|
5
|
7
|
9
|
H
|
F,G
|
4
|
7
|
10
|
Attachment:- Project Quality Management.rar