You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.
In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.
Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall.
You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.
You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.
Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation.
Develop a 6 slide powerpoint presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.
What hammurabis code tell us about woment in anceint babylon
: The Humanistic Tradition, Book 1: The First Civilizations and the Classical Legacy. Reading 1.3 from Hammurabi's code. What does Hammurabi's code tell us about woment in anceint babylon?
|
Calculate the after-tax cost of debt
: Calculate the after-tax cost of debt. Calculate the cost of preferred equity
|
Provide the type of organization and a complete description
: Create a scenario (provide the type of organization and a complete description of the task) that would be an ideal situation to employ each of the four most common types of teams: project teams, cross-functional teams, virtual teams, and self-mana..
|
Reflection of the ms dynamics product
: Create a separate section and write your own reflection of the MS Dynamics product you had selected. Your report should include proper references.
|
Place and working on receiving proper building permits
: You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
|
Write an essay on the secret history of the mongols
: Write an essay on The Secret History of the Mongols. What type of document is this? Who is the intended audience of the document? What are the main points of the document?
|
Individual retirement accounts
: For this assignment, you will prepare a PowerPoint presentation evaluating and explaining the 401(k) and Individual Retirement Accounts (IRAs) at a local community center, where you have been invited to speak.
|
Select an organization and describe its history
: Select an organization and describe its history, products, and major competitors in a paragraph or two. Develop a SWOT analysis detailing the strengths, weaknesses, opportunities, and threats that may affect the organization.
|
What are the critical success factors for retail e-business
: What is the source of expertise behind Amazon's online book recommendations and how do you feel about online merchants tracking your purchases and using this information to recommend additional purchases?
|