Performance requirements and corrective action plan

Assignment Help Project Management
Reference no: EM132395632

Engineers are working on a fix to a seismometer that does not meet the sensitivity requirements. Their research has shown gradual improvement in the item's performance, though there is no guaranteed date when the item will perform as required. What would be an appropriate step to tracking the resolution of this issue?

  • Adjust the performance requirements and corrective action plan as warranted.
  • Discuss alternative solutions with engineers and run a schedule risk analysis
  • Transfer the issue to another team.
  • Monitor the issue to collect actual vs. planned cost, schedule and performance information and review the issue at regular meetings.

Reference no: EM132395632

Questions Cloud

How does effective project integration management : How does effective Project Integration Management help to ensure that each project is managed in a unified and consolidated way
Explain the most important things to monitor in a project : Monitoring the project means you, as the project manager, are in charge and your project's health depends upon monitoring and control,
Implement and document the risk : What step of the Department of Defense (DOD) risk management process consists of the activities to develop, implement and document the risk?
Write a dissertation on Influence Of Product Attributes : Write a dissertation on: Influence Of Product Attributes, Pricing And Entrepreneurial Characteristics On The Growth Of Apparel Small And Medium Enterprises
Performance requirements and corrective action plan : Adjust the performance requirements and corrective action plan as warranted. Discuss alternative solutions with engineers and run a schedule risk analysis
Prepare a Business Plan for the CARV-TECH Compnay : Prepare a Business Plan for the "CARV-TECH" Compnay and also follow the given outline. CARV-TECH will provide computer repair.
Resourcing Talent Assignment Problem : 3RTO Resourcing Talent Assignment Help and Solution. CIPD Assessment Activity 3RTO. Describe the key factors that can affect an organisation's recruitment
Explain one consequence of using misaligned testing process : Post a brief explanation of two potential impacts of using tests not linked to job analyses. Then, explain one consequence of using a misaligned testing.
Data centre consultancy project : Analysis of Data Centre Layout and Design of the rooms & other areas within the DC facility - Capacity Analysis of the existing DC Facility & Infrastructure

Reviews

Write a Review

Project Management Questions & Answers

  Find power spectral density and the autocorrelation function

Find the power spectral density and the autocorrelation function of n(t).- What is the maximum rate at which n(t) can be sampled so that the resulting samples are essentially uncorrelated?

  Discuss the quality assurance practices

Appraise a non-technical reader the different types of quality assurance that are available. As part of your appraisal you consider at least three different quality assurance bodies.

  What is the critical path

What is the critical path? Optional: Solve this problem with Microsoft Project. How does clicking on "Tracking Gantt" view demonstrate the critical path?

  Describe the knowledge and processes areas of project

the specific course learning outcomes associated with this assignment are describe the knowledge and processes areas of

  Explain the scope of the project and control measures

Describe the scope of the project and control measures. Describe the goals and objectives of the project. Include a high-level overview of all project deliverables

  Discuss project management-project life cycle

Discuss project management, Project life cycle and project management process.

  Write a report measuring each alternative by the yardstick

Write a report measuring each alternative by the yardstick you have created. Recommend a course of action to your boss or to the organization head.

  What will you need to understand and measure

1. What will you need to understand and measure for an effective reengineering project?

  Find the total carrying cost per year

Total carrying cost per year - If it costs $2 in storage costs to hold a $10 item in storage for 1 year, the total carrying cost per year

  Demand of the consumers and stakeholders

Issues and crisis management should be part of a company''s management strategy and planning process" (p. 184).

  Create network diagram of logical sequence of all activities

Describe the project that will be the basis for your final project - Create a Network diagram of the logical sequence of all activities and describe the tasks that you would need to complete in order to close out the project.

  Ff risk factor portfolios

A portfolio manager comes up to and says: This past year my returns were 18%. The S&P 500 only delivered 12%, the Russell 2000 (a small cap index)

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd