Reference no: EM13256211
1. Consider the following precedence chart. The start date for this project is March 15, 2013.
Phase
|
Activity
|
Preceding
Activities
|
Duration (days)
|
Phase 1
|
A
|
--
|
5
|
Phase 1
|
B
|
--
|
6
|
Phase 1
|
C
|
--
|
3
|
Phase 2
|
D
|
A
|
5
|
Phase 2
|
E
|
A
|
4
|
Phase 2
|
F
|
B
|
4
|
Phase 3
|
G
|
D,E
|
5
|
Phase 3
|
H
|
F
|
5
|
Phase 4
|
I
|
H
|
3
|
a) Perform critical path analysis by hand. What is the minimum project duration?
b) Compute the total slack for each activity using the forward pass and backward pass approach.
2. A network consists of the following activities. Times are given in days.
Phase
|
Activity
|
Preceding
activities
|
Optimistic
|
Most likely
|
Pessimistic
|
Phase 1
|
A
|
--
|
5
|
9
|
15
|
Phase 1
|
B
|
--
|
3
|
6
|
9
|
Phase 1
|
C
|
--
|
5
|
12
|
15
|
Phase 2
|
D
|
A
|
3
|
5
|
7
|
Phase 2
|
E
|
B
|
4
|
6
|
12
|
Phase 2
|
F
|
C
|
6
|
8
|
10
|
Phase 3
|
G
|
D, E,F
|
2
|
5
|
6
|
Phase 3
|
H
|
F
|
3
|
4
|
9
|
Phase 4
|
I
|
G, H
|
5
|
5
|
5
|
a) Perform critical path analysis by hand. What is the minimum project duration?
b) Now use MS Project software and perform critical path analysis. Start date for this project is March 15, 2014. We use a standard calendar. When should we complete this project? Compare results from question (a) and question (b).
c) Use MS Project software and perform critical path analysis when we are introducing a lag of 3 days at the start of D and a lag of 4 days at the start of H. We are introducing a lead of 3 days at the start of F. We use standard calendar. Start date for this project is March 15, 2013. Mark I as milestone activity. When should we complete this project? The deadline is set as May 1, 2014. Can we finish this project by the deadline date? Support your answers with printouts from MS-Project software.
d) What are the WBS codes for A and G. Hint: Go to task information and find WBS codes.
Compare financials across competitors or over time
: Do you believe it would be more important to compare financials across competitors or over time? Explain your choice, giving examples.
|
Local political picnic
: At a local political picnic there are 20 male republicans, 15 male democrats adn 12 female democrats. a raffle is held to give away a nice coleman picnic cooler what is the probability that either a male of a republican will win the prize?
|
Use of chemicals and solvents in an industrial environment
: How does the concept of permissible exposure limit affect the use of chemicals and solvents in an industrial environment?
|
Operator of a summer camp-excel employment agency
: In May, Mike, a 17 years old college student, was introduced to Dover, the operator of a summer camp, through Excel Employment Agency. Mike and Dover entered into a written agreement whereby Dover hired Mike as a camp counselor during the summer vaca..
|
Perform critical path analysis-minimum project duration
: Perform critical path analysis by hand. What is the minimum project duration? Compute the total slack for each activity using the forward pass and backward pass approach.
|
A solution calorimeter has a heat capacity
: A solution calorimeter has a heat capacity of 94.82 J/K. It contains 100mL of a solution that is 3.0 M in H2SO4 and 0.02500 M in Fe2+. This solution has a heat capacity density of 0.232 J/K mL. 0.07900 g of powdered KMnO4 (FW=158.034 g/mol) was intro..
|
Scope and limitations of its own power
: Though the U.S. Constitution provides for checks and balances that limit the power of each of the three branches of U.S. government, which branch can essentially decide for itself the scope and limitations of its own power?
|
A dsDNA molecule is found
: A dsDNA molecule is found to be 14% cytosine. What are the proportions of the other three bases?
|
A fuel oil is burned in a boiler furnace
: A fuel oil is burned in a boiler furnace, releasing 2*10^7 J/hr of heat, of witch 90% goes to produce saturated steam at 1500 kPa from liquid water at 30 C. at that rate in kg/hr is steam produced?
|