Reference no: EM132258618
Regarding Federal Government Contracting:
1. _____ creates a proper corporate image of the company in the minds of customer personnel.
A. The quality, cost and timely delivery of the contract items
B. The ability, effectiveness and politeness of the personnel representing the company
C. The correspondence and reports transmitted to actual or potential customers
D. All of the above
2. From the Government’s point of view, what is the overriding issue when a performance problem surfaces?
A. Cost overruns
B. Quantity shortages
C. Extent of damage if problem is not resolved
D. Specifications not met
E. None of the above
3. Which of the following conditions may not excuse a contractor’s nonperformance?
A. Implied warranty of specifications
B. Subcontractor performance problems
C. Failure to furnish customer-furnished property
D. Impracticality of performance
E. None of the above
4. The CAO cannot perform which functions under any circumstances:
A. Negotiate prices under basic ordering agreements
B. Issue change orders
C. Prepare contractor performance evaluation
D. Accomplish closeout procedures