Reference no: EM132243661
1. Which of the following is an output of the Collect Requirements process?
Regression Analysis
Requirements Traceability Matrix
Product Design
Prototypes
2. What is a milestone?
A term used to describe a project constraint
The physical attributes of the project charter
A significant point or event in a project
A logical step in the project's progression
3. What is a logical relationship in which a successor activity cannot finish until a predecessor activity has started called?
Start to finish (SF)
Finish to finish (FF)
Finish to start (FS)
Start to start (SS)
4. Which of the following is not a dependency attribute?
Mandatory
Internal
External
Advisory
5. What is a Resource Breakdown Structure?
A chart showing logical progression of project resources required
A hierarchical representation of resources by category and type
A description of the quantities required of each resource
A grouping of the work packages
6. Which of the estimates used in Three-Point Estimating looks at the realistic expectations of availability?
Least likely
Pessimistic
Most likely
Optimistic
7. What is a method used to estimate the minimum project duration?
Critical Chain Method
Resource Optimization
Critical Path Method
Leads and Lags
8. Which of the following graphical formats is NOT listed in the PMBOK as a Project Schedule presentation?
Pie Charts
Project Schedule Network Diagrams
Bar Charts
Milestone Charts