Outline what you believe the current status of the project

Assignment Help Operation Management
Reference no: EM13748688

1. Post-Award Activity: You bid the program with a total budget of $26 millionincluding a $2 million management reserve and a BAC of $24 million to be completed in 12 months. Although we know the expenditures will not be linear, let's assume a straight-line relationship between time and budget for this exercise. At month 5 we find we should be at $10 million (BCWS) (straight-line plan of $2 million spent each month * 5 months), we have completed enough work to justify an expenditure of $8 million (BCWP) and our actual costs accrued to date are $7 million. (ACWP)

1. Outline what you believe the current status of the project is and interpret what the projections mean to you. Using only this cost data, how can you project time to complete?

2. Outline what you believe the action plan should be to bring this project in on-schedule, on-budget and meet the customer requirements.

2. Understanding Total Cost of Quality and Risk: System Engineers are constantly trying to balance the cost of prevention and appraisal with the risk of failure. Please review the TASER Total Cost of Quality article, found in the ASQ magazine - starting on page 13- (eighth article from the bottom in the Course Documents folder), and use this as a reference:

a. You have considered your repair organization as a profit center in the past. Please develop a compelling argument on why TASER should invest more in prevention and appraisal.

b. Assuming you win the argument above, develop a detailed outline of how you would make this transition. What are the logical steps to success?

3. BPMN: This modern modeling technique from OMG can have significant impacts on all aspects of Systems Engineering:

a. In your opinion what are these Systems Engineering implications as we attempt to migrate to the Model-based Enterprise?

b. If BPMN AND BPEL ultimately do what is projected they can do, what will be the Systems Engineering implications on:

i. Requirements Definition, Requirements Capture and Requirements Creep?
ii. Configuration Management?
iii. Project Management?
iv. Risk Management?

4. Predicting Costs: The Knox predictive model shows that the more rigor an organization has (increased SEI level), the lower the total cost of the system development.

a. CoCoMo and CoSysMo take this into account in subtle ways. Please review the CoCoMo and CoSysMo methodologies and comment on how "Rigor ~ e.g. increased SEI level", is factored into the calculations. Do this ONLY from a qualitative viewpoint ~ I do NOT expect that you do this from a quantitative viewpoint nor do I expect that you show the quantitative effects of this. I am seeking a qualitative "where is rigor factored into the concepts" rather than into the equations here!

b. In CoSysMo we use the factor "A" - the calibration constant. How would you develop a verified and validated "A"?

5. Mitigating Risk:We addressed the pressure cooker FMEA exercise in class. There are various ways of mitigating risks such as: adding redundancies, reducing the impact, reducing the probability, pushing the risk to someone else, etc.As a Systems Engineer how do you propose to create an "excellent" solution for the pressure cooker risks we encountered from two perspectives? Here I am not looking for solutions, I am looking for the Systems Engineering process.

a. A Technical Perspective

b. A Business Perspective

Reference no: EM13748688

Questions Cloud

Age of confessional division produced religious war in spain : During the 16th century, The Age of Confessional Division produced religious wars in France, Spain, and the Netherlands. Choose one of these conflicts and discuss the events, causes, and outcomes.
Market value of a corporate bond : The market value of a corporate bond with a fixed interest rate will _____ if interest rates in the overall economy decrease.
What impact did the price revolution have on the governments : What impact did the Price Revolution have on the governments and people of Europe?
Sell or process further : Port Allen Chemical Company processes raw material D into joint products E and F. Raw material D costs $4 per liter. It costs $100 to convert 100 liters of D into 60 liters of E and 40 liters of F. Determine whether Product F should be sold or proces..
Outline what you believe the current status of the project : Outline what you believe the current status of the project is and interpret what the projections mean to you. Using only this cost data, how can you project time to complete
What do you think of the myth of the lost cause : what do you think of the myth of "The Lost Cause?" Do you think that the Confederacy was fighting for something honorable? Was it fighting against northern aggression or for something else?
What are the steps and what is the easiest way : Solve for X : 4x+23400-12=800x-4(x-12)How would I solve this question? What are the steps and what is the easiest way to figure it out?
How companies and countries are becoming specialised : Comparative advantage - How companies and countries are becoming specialised in certain industries to compete and expand their businesses. Compare Australia with any other country.
The product becomes less competitive and sales drop : Assume that we produce only what we sell. Let P be the selling price in dollars per gallon. Suppose that the selling price and the sales quantity Q are interrelated as follows: Q 6 106 1.1 106P. Accordingly, if we raise the price, the product becomes..

Reviews

Write a Review

Operation Management Questions & Answers

  Compare and contrast these factors to those most important

Which factors do you think influence employee job satisfaction? Compare and contrast these factors to those most important to you.

  Calculate the current multifactor productivity

Charles Lackey operates a bakery in Idaho Falls, Idaho. Currently, the bakery has 4 employees, each one working 160 hours per month. Because of its excellent product and excellent location, demand has increased by 30% in the last year.

  Relationship of strategic objectives information to pmo

Explain the relationship of strategic objectives information to PMO outpuits. Explain how executives might be operating today without this information.

  Discuss what working capital is and how it is relevant

Discuss what working capital is and how it is relevant to cash budgeting.

  Case study - motorola

Motorola obtains cell phones from its contract manufacturer located in China to serve U.S. market. The U.S. is served from a warehouse located in Memphis, Tennessee.

  What green systems are the company using in the future

What green systems are the company using or planning to use in the future. How do decisions regarding each of these three concerns affect decisions regarding the other two

  Emphasize the advantages of the project and the value of

write a brief opening statement for your microsoftreg powerpointreg presentation in which you reiterate project

  Write strategic objectives summary

Develop at least three strategic objectives for each of the four balanced scorecard areas identified (Financial, Customer, Process, Learning and Growth). Your objectives should be selected, in part, based on an evaluation of a number of potential ..

  Illustrate what should be the actual cycle time

They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day. The subsequent table describes the tasks necessary to produce this product.

  Compare and contract unsecured credit and secured credit

Compare and contract unsecured credit and secured credit, and explain the key differences. Provide an example for each.

  Describe the type of project you worked on

Describe how you reviewed the contracting and procurement activities on each project you worked on previously and describe the type of project you worked on.

  Discuss an ineffective health care policy

Discuss an ineffective health-care policy that you personally experienced in your practice, and describe the issues that you feel made it unsuccessful.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd