Original cost estimate and cost performance index

Assignment Help Business Management
Reference no: EM13229941

Huston Power, Inc., (HPI), an electrical power-generating company, has hired your firm to refurbish one of its gas turbine units. The manufacturing department works only on the day shift. The staff of the manufacturing department is paid on an hourly basis and is paid one-and-a-half times the salary for working overtime.

Given below are the staff salaries.

Resource

Hourly Rate (€)

Notes

Project manager

50


Lead engineer

45


Design engineer

40


Software engineer

40


Hardware engineer

40


Manufacturing staff

150

The manufacturing staff consists of six people.

Installation staff

75

The installation staff consists of three technicians.

The project plan is as follows:

Task #

Description

Duration (days)

Start

Finish

Predecessor

1

Acceptance of the contract

0

1/4

1/4


2

HPI engineering site survey

3

1/4

1/6

1

3

Hardware design

14

1/7

1/26

2

4

Human-Machine Interface (HMI) software design

20

1/27

2/23

3

5

HMI software development

25

3/24

4/29

11

6

Software integration and testing

10

4/30

5/14

5

7

Unit 1 hardware testing

3

2/10

2/12

17

8

System testing

5

5/17

5/21

6,7,3

9

HPI factory acceptance test (FAT)

5

5/24

5/28

8

10

Customer-witnessed FAT

5

6/1

6/7

9

11

Functional design specification

20

2/24

3/23

4

12

HPI review design documentation

2

2/24

2/25

4

13

Customer review functional design

5

2/26

3/4

12

14

Preparation of FAT specifications

2

1/27

1/28

3

15

Creation of the operations and maintenance manual

10

6/8

6/21

10

16

Final documentation

4

7/19

7/22

25

17

Manufacture unit 1

10

1/27

2/9

3

18

Delivery to the site

4

6/22

6/25

15

19

Travel to the site for installation

1

6/25

6/25

18FF

20

Demolition: Control panel

2

6/28

6/29

19

21

Installation: Control panel

8

6/30

7/9

20

22

Installation: Fuel system

2

7/12

7/13

21

23

Travel from the site after installation

1

7/14

7/14

22

24

Travel to the site for commissioning

1

7/14

7/14

23FF

25

Checking of the cold loop

2

7/15

7/16

24

26

Checking of the hot loop

4

7/19

7/22

25

27

Commissioning

3

7/23

7/27

26

28

Training of the client's team in operations

3

7/28

7/30

27

29

Training of the client's team in maintenance procedures

1

8/2

8/2

28

30

Procurement of customer acceptance

0

8/2

8/2

29

31

Travel from the site after commissioning

1

8/3

8/3

30

32

Project closure

2

8/4

8/5

31

33

Project management

150

1/4

8/5

1

The resource usage, by task, is as follows:

Task Name

Resource Names

Acceptance of the contract


HPI engineering site survey

Lead engineer

Project management

Project manager

Hardware design

Design engineer

HMI software design

Design engineer

Preparation of FAT specifications

Lead engineer

Manufacture unit 1

Manufacturing staff

Unit 1 hardware testing

Hardware engineer

Functional design specification

Design engineer

HPI review design documentation

Lead engineer

Customer review functional design


HMI software development

Software engineer

Software integration and testing

Software engineer

System testing

Lead engineer

HPI factory acceptance test (FAT)

Lead engineer

Customer-witnessed FAT


Creation of the operations and maintenance manual

Design engineer

Delivery to the site


Travel to the site for installation

Installation staff

Demolition: Control panel

Installation staff

Installation: Control panel

Installation staff

Installation: Fuel system

Installation staff

Travel from the site after installation

Installation staff

Travel to the site for commissioning

Lead engineer

Checking of the cold loop

Lead engineer

Final documentation

Design engineer

Checking of the hot loop

Lead engineer

Commissioning

Lead engineer

Training of the client's team in operations

Lead engineer

Training of the client's team in maintenance procedures

Lead engineer

Procurement of customer acceptance


Travel from the site after commissioning

Lead engineer

Project closure

Lead engineer, design engineer, software engineer

Your company observes UK holidays. For 2010, these holidays are:

January 1

New Year's Day

April 2

Good Friday

April 5

Easter Monday

May 3

Early May Bank Holiday

May 31

Spring Bank Holiday

August 30

Summer Bank Holiday

December 27

Christmas Day

December 28

Boxing Day

If the project starts on January 4, it will finish on August 5. The contract with Huston Power, Inc. includes penalties if the project completes later than August 5. As of February 26, the following tasks have been completed:

Task Name

Start

Finish

Duration (days)

Acceptance of the contract

1/4

1/4

0

HPI engineering site survey

1/4

1/6

3

Hardware DESIGN

1/7

1/27

15

HMI software design

1/28

2/26

22

Unit 1 hardware testing

2/11

2/17

5

Preparation of FAT specifications

1/28

2/1

3

Manufacture unit 1

1/28

2/10

10

Using the data provided, calculate the following:

The original cost estimate

The new cost estimate as of February 26

Changes that can be made to the schedule to complete the project by August 5

The planned value (PV) as of February 26

The actual cost (AC) as of February 26

The earned value (EV) as of February 26

The value of the following as of February 26:

Cost variance (CV)

Cost performance index (CPI)

Schedule variance (SV)

Schedule performance index (SPI)

Estimate to complete (ETC)

Estimate at completion (EAC)

Reference no: EM13229941

Questions Cloud

Explain the glycerophosphate shuttle in insect flight muscle : How many ATPs are synthesized for every cytoplasmic NADH that participates in the glycerophosphate shuttle in insect flight muscle?
What is the net income for this firm : Lifeline, Inc., has sales of $585,000, costs of $273,000, depreciation expense of $71,000, interest expense of $38,000, and a tax rate of 35 percent. What is the net income for this firm?
What is the required rate of return on a stock : Assume that the risk-free rate is 7.0% and the expected return on the market is 8%. What is the required rate of return on a stock with a beta of 1.4? Round your answer to two decimal places.
Explain how to achieve the maximum electric field : A Si (ni = 1 e+10 cm^-3, eps = 11.7) p-n junction is doped with NA = 5.2 e+18 cm^-3 and ND = 8.4 e+14 cm^-3. What reverse bias (the absolute value) should be applied to the junction, in order to achieve the maximum electric field of 3.89E+4 V/cm
Original cost estimate and cost performance index : Cost performance index, schedule variance, schedule performance index, estimate to complete (ETC) and estimate at completion (EAC)
Does this mean that the asset has negative risk : Why would anyone ever invest in an asset that has an expected and required return that is negative? Explain.
Explain sodium hydroxide solution : What would happen if the buret washed and rinsed properly but not conditioned with sodium hydroxide solution, prior to standardizing the sodium hydroxide solution?
What will be the companys return on equity : Management projects an EBIT of 1,000,000 on sales of 10,000,000 and it expects to have a total assets turnover ratio of 2.0, under these conditions, the tax rate will be 34%. If the changes are made, what will be the company's return on equity?
Show the flow of holes and electrons under the conditions : When electros and holes are present in a semi-conductor, the presence of an electric field produced by an external voltage will cause this carries,which have changes of oposite sign, to move in opposite directions.

Reviews

Write a Review

Business Management Questions & Answers

  Caselet on michael porter’s value chain management

The assignment in management is a two part assignment dealing 1.Theory of function of management. 2. Operations and Controlling.

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. Due to increase in the preference for light beer drinkers, Chris Prangel wants to introduce light beer version in Mountain Man. An analysis into the la..

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. An analysis into the launch of Mountain Man Light over the present Mountain Man Lager.

  Analysis of the case using the doing ethics technique

Analysis of the case using the Doing Ethics Technique (DET). Analysis of the ethical issue(s) from the perspective of an ICT professional, using the ACS Code of  Conduct and properly relating clauses from the ACS Code of Conduct to the ethical issue.

  Affiliations and partnerships

Affiliations and partnerships are frequently used to reach a larger local audience? Which options stand to avail for the Hotel manager and what problems do these pose.

  Innovation-friendly regulations

What influence (if any) can organizations exercise to encourage ‘innovation-friendly' regulations?

  Effect of regional and corporate cultural issues

Present your findings as a group powerpoint with an audio file. In addition individually write up your own conclusions as to the effects of regional cultural issues on the corporate organisational culture of this multinational company as it conducts ..

  Structure of business plan

This assignment shows a structure of business plan. The task is to write a business plane about a Diet Shop.

  Identify the purposes of different types of organisations

Identify the purposes of different types of organisations.

  Entrepreneur case study for analysis

Entrepreneur Case Study for Analysis. Analyze Robin Wolaner's suitability to be an entrepreneur

  Forecasting and business analysis

This problem requires you to apply your cross-sectional analysis skills to a real cross-sectional data set with the goal of answering a specific research question.

  Educational instructional leadership

Prepare a major handout on the key principles of instructional leadership

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd