Normal level of activity for the project

Assignment Help Business Management
Reference no: EM13979325

Problem 1: Given the information provided below (predecessors, normal time, normal cost, crash time (the minimum duration) and crash cost (the cost if crashed to the minimum duration) for an nine-activity (a to i) project) answer the questions (a) through (e) using this template.

Activity

Predecessor

Normal Time

Normal Cost

Crash Time

Crash Cost

a

-

4

$ 50

2

$ 150

b

a

4

$ 40

2

$ 200

c

b

7

$ 70

4

$ 160

d

c, f

2

$ 20

1

$ 50

e

c

3

$ 30

2

$ 100

f

b

8

$ 80

5

$ 290

g

d, e

5

$ 50

3

$ 100

h

f

6

$ 60

2

$ 180

i

g, h

3

$ 50

3

$ 50

(a). Create the network diagram in the application of your choice and then insert a screen shot of the diagram here. The diagram can be created easily in MS Word using the Insert Shapes function.

Identify the critical path of the network, the time, and cost of the normal level of activity for the project:

  • The critical path (or paths) is: __________________
  • The project duration: ___________
  • The project cost is: _____________

(b). Calculate the crash cost-per-day (all activities may be partially crashed). Enter your response to question 1(b) in the table provided below

Activity

Normal Time

Normal Cost

Crash Time

Crash Cost

Crash Cost/Day[1]

a

 

 

 

 

 

b

 

 

 

 

 

c

 

 

 

 

 

d

 

 

 

 

 

e

 

 

 

 

 

f

 

 

 

 

 

g

 

 

 

 

 

h

 

 

 

 

 

i

 

 

 

 

 

(c). Find the optimal way to crash the project by one day.

  • What is the projected project cost?
  • What is the projected project duration?
  • What is the critical path (or paths)?
  • What task or tasks were crashed?

Explain the results of your calculations.

(d). Find the optimal way to crash the project by two days.

  • What is the projected project cost?
  • What is the projected project duration?
  • What is the critical path (or paths)?
  • What task or tasks were crashed?

Explain the results of your calculations.

(e). Calculate the shortest completion time for the project.

  • What is the projected project cost?
  • What is the projected project duration?
  • What is the critical path (or paths)?
  • What task or tasks were crashed?

Explain the results of your calculations.

[1] Assume that each task's crash costs are linear, ie that each day a task is crashed has an equal cost.

Reference no: EM13979325

Questions Cloud

Satisfied with the level of customer service : A commercial bank is concerned about its image among its clients. In a random survey that was run last year among 500 clients, 54% said that they were satisfied with the level of customer service. This year, in another survey among 400 clients, only ..
Determine the capitalized cost for each design : Two incinerators are being considered by a waste management company. Design A has an initial cost of $2,625,000, has annual operating and maintenance costs of $950,000, and requires overhauls every 5 years at a cost of $1,650,000. Using a 8.0 %/year ..
What is the combined effect of curvature : What is the combined effect of curvature and refraction for a 300 foot long level shot - An equal tangent vertical parabolic curve has the characteristics
Sharing confidential information : We are each faced with ethical decisions. Using your readings as a foundation, please describe an ethical situation you have experienced in your professional practice and how it was resolved. Please be as specific as possible while not sharing con..
Normal level of activity for the project : Create the network diagram in the application of your choice and then insert a screen shot of the diagram here. The diagram can be created easily in MS Word using the Insert Shapes function. Identify the critical path of the network, the time, and..
Find the magnitude and direction of the total magnetic field : At some instant, an alpha particle(q=+2e) has the coordinates(3.0,0.0,0.0)(nm) and is moving along the positive x-axis with 500km/s while an electron at (0.0,4.0,0.0)(nm) is moving along the negative y-axis with 1000km/s. Find the magnitude and di..
What do you understand from curl and div of a vector field f : What do you understand from Curl and Div of a vector field F? Explain them with examples. Is there any difference between Grad and Div of F? What are the applications of Grad, Div and Curl? Define Contra positive, Converse, and Inverse of a statement..
What was the cars velocity when it passed the checkpoint : A speeding car passes a highway patrol checkpoint and thendecelerates at a constant rate. What was the car's velocity when it passed the checkpoint? What was the acceleration of the car?
What is supply and demand how do they differ : What is Supply and Demand? How do they differ?

Reviews

Write a Review

Business Management Questions & Answers

  Illustrate what does the research on employee stress suggest

Illustrate what does the research on employee stress suggest you should do to help minimize the experience of psychological strain of employees?

  Paraphrase oconners passages

Read the following paragraphs, which were written by Patricia O'Conner. A good writer is one you can read without breaking a sweat. If you want a workout, you don't lift a book?

  The shut down rule in the short run

Discuss the shut down rule in the short run.

  Strategic planning and considering external factors

How would you assess the attitude of a society, especially a heterogeneous one like we find in many big cities in the US and around the globe

  Create a capital investment plan

You will create a capital investment plan proposal utilizing the health care business you selected in Week One as well as the answers to the Basic Information questions.  Refer to the websites for Sample Business Plans.  Create a capital investmen..

  Describes a successful change initiative within organization

Describes a successful change initiative within an organization. Next, locate and discuss a scholarly article that describes a failed change initiative within an organization.

  Explain higher level management within organizations

Determine ways you plan to apply what you learned in this course to your current or future position. Create a persuasive argument of this type of course being a requirement for higher level management within organizations.

  Explain brand distribution channels

Pick a health as well as beauty brand and item you use regularly for instance shampoo, moisturizer, shaving cream, razor blades and so on. Imagine this brand is spreading its reach to a new target audience with a new product, Explain brand Distrib..

  Portfolio of core competences

1) Review Hamel & Prahalad's view of a company as a "portfolio of core competences" (Chapter 8, pp. 205-208, and Figure 8.2 on p. 206). Based on those competencies or others you now recognize, can you think of "fill-in-the-blanks" opportunitie..

  New products customers and marketsthe home page of this

new products customers and marketsthe home page of this module identifies several measures of the learning perspective

  Use marketing information to differentiate

Recommend two (2) ways in which a company within the selected product group could use marketing information to differentiate itself in the marketplace to gain an advantage over its competitors. Provide a rationale to support your recommendations.

  Analyzing the integrated business communication

Write a three to four (3-4) page paper addressing the following: Identify the Web site, the sender, and perceived receiver. Analyze the integrated business communication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd