Nbspq1table 1 indicates the sequence and interdependence of

Assignment Help Project Management
Reference no: EM13351229 , Length: Word count:1500

 

Q1.

Table 1 indicates the sequence and interdependence of the 10 activities (A - K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table

Activity

Description

Duration (wks)

Precedence

A

Requirement Gathering

27

-

B

Business Analysis

24

-

C

Systems Analysis

21

-

D

Coding

21

A

E

Unit Test

22

B

F

Module Testing

27

C

G

Systems Testing

22

F

H

User Acceptance Testing

22

G,E

J

Implementation

22

H

K

Handover

23

D, J

(a) Construct a network diagram identifying the following:

i. Earliest Start Time(EST)
ii. Latest Finish Time (LFT)
iii. Total Float on each activities D, F & J
iv. Critical Path for the project

b) Assume that there is a delay of 3 weeks in completing activityH. Analyseone action that the Operations Manager could take to avoid exceeding the current length of the critical path.

Q2.

The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?

Differentiate and accurately distinguish between the need for organised interaction between the role of design and management within operations strategy.

Word count:1500

Reference no: EM13351229

Questions Cloud

Q1 a football player runs directly down the field for 16 m : q1. a football player runs directly down the field for 16 m before turning to the right at an angle of 33 from his
You are a high level manager who has been asked to show a : you are a high level manager who has been asked to show a powerpoint presentation to your employees on the ideas of
Q1 over a 30-day period a power plant generates an average : q1. over a 30-day period a power plant generates an average of 751 mw of electrical power and 1225 mw of waste heat and
Q1 physics instructor wants to produce a double-slit : q1. physics instructor wants to produce a double-slit interference pattern large enough for her class to see. for the
Nbspq1table 1 indicates the sequence and interdependence of : nbspq1.table 1 indicates the sequence and interdependence of the 10 activities a - k which together are required to
Q1 a jewel thief hides a diamond by placing it on the : q1. a jewel thief hides a diamond by placing it on the bottom of a public swimming pool. he places a circular raft on
Q1 a weather vane initially at rest has a moment of inertia : q1. a weather vane initially at rest has a moment of inertia of 0.111 kg bull m2 about its axis of rotation. a 53.0 g
Q1 sound waves of frequency 502 hz enter a window 118 m : q1. sound waves of frequency 502 hz enter a window 1.18 m wide. the window is in the exact center of one wall of a
Q1 starting from rest a basketball rolls from the top of a : q1. starting from rest a basketball rolls from the top of a hill to the bottom getting a translational speed of 7.36

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd