The? post-project review of the Alpha Supplement project is complete. It found failures in planning. Too much time was budgeted to market? research, leaving not enough time for product development and quality assurance. As a? result, the project could not have succeeded even if the project had been run perfectly. But there were other problems as well. Constant conflicts between team members demonstrated a failure of leadership.? Finally, there were failures in controlling. When component providers failed to? deliver, project leaders did not locate and train new providers in time.
Which of the following is most strongly suggested by the statements? above?
A. The problems that affected the Alpha Supplement project were typical of the problems affecting projects in this organization.
B. There were no actions that the project leaders could have taken that would have solved the controlling problems of the Alpha Supplement project.
C. The insufficient time allocated for product development was the only failure related to planning.
D. If the project leaders had located alternate component? providers, the Alpha Supplement project still would have failed.
E. The failure of the Alpha Supplement project will make it more difficult for other projects to be approved.