Monte Carlo Simulation Coursework and Report

Assignment Help Project Management
Reference no: EM133037278 , Length: word count:500

Project risk management

Monte Carlo Simulation Coursework and Report

Coursework Part A: How Many Souvenir Books to Produce?

The first part of the coursework concerns a decision about a production batch size for a major event next summer. "Taking place over the weekend of Saturday 14th and Sunday 15th August 2021 at INTU BRAEHEAD, Film & Comic Con Glasgow promises a fun weekend where you can meet celebrity guests, browse the many trader stalls, get hard to find items and enjoy some cosplay, a must for all fans of pop culture."
The "Movie Merchandise Company" plans to produce a batch of souvenir books to sell during the weekend of Comic Con. The book has been designed and priced, but it has not yet been decided how many to produce. The company want to choose the batch size that will maximise their profits. In order to help them make the right decision they have asked you to perform a Monte Carlo simulation analysis of the expected profits. They have provided you with the following information:

It is known that there will be fixed production costs of £10,000.
There will also be variable production costs. For each book the company produce there will be an additional cost of £5.
The revenue from each book sold will be £12.
After doing some extensive market research it predicts that customer demand for the book will be normally distributed with a mean value of VARIABLE 1 and a standard deviation of VARIABLE 2.
Remember, the company cannot sell more books than it has produced - whatever the demand. It is also assumed that there is no cost for disposing of any surplus books that are not sold.
Due to a number of manufacturing constraints the options for the production batch size are either VARIABLE 3 or VARIABLE 4. That is the decision the company has to make and about which you have to advise them.

On the basis of your simulation analysis, you should provide the necessary information for the company to make its decision. In particular, what are the expected profits for each production batch size? You should consider the key statistics (mean, maximum profit etc) and a graph of the frequency distribution.

Coursework Part B: Predict the Project Duration Time

The company in part A also has to plan when to start this particular project in order to have the books ready in time for Comic Con which will take place during August 2021. The books will be on sale at INTU BRAEHEAD when the event is taking place - but not available anywhere else or at any other time. Bear in mind, the company has many other projects in progress, and does not have much space to store finished goods before they are sold.

It has drawn up a project plan for the various stages of this project - including manufacturing, packaging and marketing. They have identified the 10 main activities and the dependencies between them. They have also predicted the duration time (in days) for each activity. In each case, duration times are best modelled by a Normal* probability distribution with the given means and standard deviations.

This information is in the table below:

 

Activity

 

Depends on

Estimated Duration (Days)

Mean

Standard Deviation

A

-

20

5

B

A

24

6

C

A

28

7

D

B, E

20

5

E

C

VARIABLE 5

VARIABLE 6

F

C

24

6

G

F

20

5

H

D

24

6

I

H, G

16

4

J

I

20

5

Your task is to find the expected duration of the whole project and then help the company decide when it should start. There is a file on Moodle (Souvenir Book Project) that has been set up to help you.

*A sample of manufacturing times were collected from a number of similar projects and are shown in Appendix A. You may want to analyse this data and discuss whether the choice of the Normal distribution is really suitable.

Presentation. Each group should prepare a video recorded powerpoint presentation (between 10 and 12 minutes) about the outcomes of their risk assessment. This should be directed towards the company and help them make the decisions they have consulted you about (preferred batch size and production start date). In preparing your presentation you should pay particular attention to the issue of risk communication; consider carefully how it would be best to present your findings to the company. Think about the best use of words, numbers, tables, graphs, diagrams, labels - or something else? Will your results be correctly understood?

Spreadsheet. Your group should submit a spreadsheet showing your calculations for Parts A and B. (Calculations of expected profits for both batch sizes and project duration time). The spreadsheet should also include a separate sheet that describes briefly how you have reached your conclusions. It should also include a brief section where you discuss technical issues such as the choice of the correct probability distributions and the number of iterations or repetitions to run; do you think your models and results are realistic? You might also include some brief comments about any extreme or unusual results.

Report: Qualitative versus Quantitative Risk Assessment

Once your group has finished the coursework you should write (individually) a short report reflecting on the 2 different types of risk assessment you have studied in this module - qualitative and quantitative. What do you think are the similarities and differences between the two approaches? What are their key advantages and disadvantages? You should consider the application of risk management in your chosen discipline (project or supply chain management) - what would be some of the practical issues in that discipline when conducting risk assessments. (Word count approximately 500)

Attachment:- Project risk management.rar

Reference no: EM133037278

Questions Cloud

Core characteristics of great creative minds : Relate the characteristics to the positive and negative repercussions in the lives of people who demonstrate extreme levels of creativity.
How much interest is included in the future value : How much interest is included in the future value of an ordinary simple annuity of $800 paid every six months at 4% compounded semi-annually
Changes of paramount importance : Businesses use information systems at all levels of operation to collect, process, and store data. Management aggregates and disseminates this data in the form
Compute the book value per share for the preference share : Compute the book value per share for the Preference share assuming dividends are in arrears for 3 years including the current year
Monte Carlo Simulation Coursework and Report : Monte Carlo Simulation Coursework and Report - How Many Souvenir Books to Produce - you should provide the necessary information for the company
What the after tax cost of debt for tangshan mining : The firm's tax rate is 33 percent. Given this information, what the after tax cost of debt for Tangshan Mining
Issues associated with business data mining activities : Describe legal issues associated with business data mining activities, including specific laws governing data mining practices.
Benefits of tricare for an active military person : Summarize the benefits of TRICARE for an active military person.
Assessing the organizational benefits : You are a former Navy officer and fighter pilot who is now the controller of a division of TransGlobal Airlines, which utilizes a fleet of corporate jets for ch

Reviews

len3037278

11/28/2021 10:29:06 PM

Could you see it my assignment part B individual assignment only 500 word,any other documents need please tell me.

Write a Review

Project Management Questions & Answers

  Explain how project risk assessment techniques

Project management - Please provide examples of how project risk assessment techniques can be applied to a project in the health care field.

  Project management recommend scope creep controlled

How do the worldwide standards for project management recommend scope creep controlled when unauthorized add-ons creep into a project?

  Mitigate the risks for each contract type

What are some methods that can be used to mitigate the risks for each contract type.

  How do chaos and complexity differ from one another

How do chaos and complexity differ from one another? Propose three concepts from the book that might be used to solve the issue.

  What is the value to the united states of the seignorage

What is the value to the United States of the seignorage associated with these overseas dollars? Assume that dollar interest rates are about 6%.

  Discuss the basic dimensions of good project management

Discuss the basic dimensions of good project management and provide an example to support your response.

  How can workout update its facility to attract new customers

How can Workout update its facility to attract new customers? What additional equipment or services would you suggest? How could something as simple as revising the layout help?

  Describe the four basic types of project organization

Describe the four basic types of project organization and describe the project characteristics of each organization in relation to the project manager's.

  State laws affected the employment selection process

How has the passage and enactment of numerous federal and state laws affected the employment selection process?

  What other two or three data collection approaches

What other two or three data collection approaches to measuring the success of a Web site might be fruitful in providing more meaningful data than just clicks?

  Justify their ongoing presence in the channel

What are the major differences you have experienced in buying a product through a traditional retail store, a manufacturer's store, a catalog, and an online merchant?

  Write two reflective journal entries

Write two reflective journal entries one about your learning experience and the topic (s) you learned in (Week 6 and Week 7) that is Reflective Journal

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd