MMN221207 - Project Management - Glasgow Caledonian University

Brief for Queen St project

The third busiest railway station in Scotland, Glasgow Queen Street, is being expanded to form a larger facility with superior services for growing passenger numbers. Announced in 2014, the station redevelopment will be part of the £742m Edinburgh - Glasgow Improvement Programme (EGIP). The station currently handles approximately 20 million passengers a year, and this is estimated to grow to 28 million by 2030. Use the following link as the starting point for a discussion relating to the "Queen Street Redevelopment Project, Glasgow":Queen St Station -redevelopment - Network Rail

Immediately on receipt of contract award, the project team will commence the activities required to mobilise the project. These include:
• Completion of the Construction Phase Plan (CPP) and PMP
• Environmental Management Plan with Site Waste Management Plan
• CDP Design Management Plan
• Construction Programme, methodologies, phasing plans and Traffic Management Plans.
• Supply Chain procurement
• Liaison with Public Utilities to agree a programme for their works
• Consultation with project stakeholders.
• Local community engagement
• Establishment of the Project office and welfare facilities

At the point of site establishment by the contractor this will constitute the beginning of the planning envelope and as previously outlined, encapsulates elements 1-5.

To give an indication of the comprehensive nature of new steel structure [indicated within the area shown in green in Figure 2 on p 4], a steelwork sequence image is shown below in Figure 3.

TASK ONE: WRITTEN REPORT

The third busiest railway station in Scotland, Glasgow Queen Street, is being expanded to form a larger facility with superior services for growing passenger numbers. The station redevelopment will be part of the £742m Edinburgh - Glasgow Improvement Programme (EGIP). The station currently handles approximately 20 million passengers a year, and this is estimated to grow to 28 million by 2030.Use the following link as the starting point for a discussion relating to the "Queen Street Redevelopment Project, Glasgow":

You should critically analyse the importance of project planning/schedulingfor this project. Working individually, you are to write a report (using headings and subheadings) as set out in the task above. You are required to further research the subject and all of the work must be fully referenced and all sources of information must be correctly identified and cited within the text. The Harvard System of referencing

TASK TWO: SOFTWARE PROJECT PLANAND SUMMARY

The Queen Street Redevelopment Project will take approximately 3 years (36 months)to demolish existing buildings and to complete the new build requirements. Your project director has tasked you with creating a new project plan usingAstaPowerproject because he has concerns with the existing plan.

You are to create a project plan demonstrating good logic and relevant functionalities of the software. Before you complete the Queen StreetProject plan, you should work through the in class tutorial. In order to create the Gantt Chart you will need to consider:

• The tasks involved in the project (maximum of 40)
• The durations for each task
• The logic and linking of the programme (start to start; finish to finish; start to fining; or finish to start). Further research on the topic should also help with this element.
• Show the critical path on your programme

Once you have completed your project plan, you should write a 500-word report supporting your software output. This should include justification of the "logic" used, a discussion on the key dependences of some of the main activities, as well as any other observations which you feel explains your approach.

Attachment:- Project Management.rar

Reference no: EM132492303

Questions Cloud

Identify and explain accounting principles : Mr Chan, one of the owners of Flyfli took $500 from the company's cash account and instructed the accountant to record it as an expense.
Which entities would form part of the tmhl group : Which entities (if any), would form part of the Traffic Management Holdings Ltd Group. Traffic Management Holdings Ltd (TMHL), a public company, commenced
Create a relative frequency histogram of YY : Create a relative frequency histogram of YY. Support your assertion above by performing a Chi-squared test of best fit with a 0.05 level of significance
How technology and social roles are connected : Since you have been looking at how technology and social roles are connected in this week's discussion you will take on the role of a debater on the side.
MMN221207 Project Management Assignment : MMN221207 Project Management Assignment help and solution, Glasgow Caledonian University - assessment writing service - Queen Street Redevelopment Project
What does it mean to be human : What Does it Mean to Be Human? Please prepare a paper of at least five pages in which you take and defend a position on the question of what it means to be.
How good was the teacher at supporting transition in class : How good was the teacher at supporting transition in the class? Do the questions demand the use of critical thinking and problem-solving skills?
What is the outflow to purchase inventory : What is the Outflow to purchase inventory and Outflow for sales tax? Prepare the income statement, balance sheet, and statement of cash flows for 2018.
What is value to user of the classifying the balance sheets : What is value to the user of the classifying the balance sheets further? Identify a potential user of a classified balance sheet and one significant item

Reviews

len2492303

4/14/2020 3:08:52 AM

good morning dear project team you will find in second attach more information about station also there is link to video also give more information for may assiment (pleas notice more refrence more mark) the project tow task pleas becarfual and saprt them

Write a Review

Project Management Questions & Answers

  Construct a payoff table and a decision tree diagram

If he ignores the trips, he will owe $14,000 in taxes. Construct a payoff table and a decision tree diagram for this decision situation.

  Create level three product work breakdown structure

Write 10 system performance requirements. Write 5 subsystem performance requirements for each of 2 subsystems. Create level 3 product Work Breakdown Structure.

  What is the set of possible actions and related outcomes

What is the set of possible actions and related outcomes?- What is the payoff of each action/outcome?- Draw the associated decision tree. What will a rational player choose?

  Which plant offers the lowest total? cost

If annual demand is expected to be 10 million? units, which plant offers the lowest total? cost?

  What enforcement and punitive measures will be included

What reporting and investigative measures will you put into place? What enforcement and punitive measures will be included?

  A set large scale development projects

Assume a firm works on a set large scale development projects, in which the learning curve theory can be utilized. The first project takes 200 days and the second project takes 180 days. Which of the following statements is correct A - The third pro..

  Grainger manufacturing inc produces outdoor grills on march

grainger manufacturing inc. produces outdoor grills. on march 31 the company had 120 grills in inventory. the companys

  Probability of completing the project on time

If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project?

  What is stew leonards value proposition

What is Stew Leonard's value proposition?-  How has Stew Leonard's applied the concepts of customer equity and customer lifetime value?

  Describe the facts that led to this decision

Using a search engine or one of the tax directory sites provided in Exhibit 16-6 (Chapter 16), find the 1987 Supreme Court decision that provides the current criteria for determining what constitutes a trade or business. Trace the process you used..

  Identify an important managerial challenge facing

Identify an important managerial challenge facing his or her work or other organization - Develop a plan that integrates effective financial and operational

  Prepare strategies to manage project resources

Analyze and develop project schedules with appropriate techniques and software tools. Prepare strategies to manage project resources to include human resources, capital equipment, and time.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd