1. Allen Machines specializes in developing weed-harvesting equipment that is used to clear small lakes of weeds.  Allen Machines is contemplating the construction of a machine that would harvest weeds on narrow rivers and waterways.  The activities and time in weeks necessary to build one of these experimental machines are shown in the table below.

Activity

Immediate Predecessors

Time in Weeks

A

none

6

B

none

5

C

A

3

D

A

2

E

B

4

F

B

6

G

C,E

10

H

D,F

7

1. What is the minimum possible time required for completing the project?

2. What is the latest possible time that Activity D may be started without delaying the completion of the project?

3. What is the latest finish time for Activity F?

4. What is/are the critical path(s)? 

Reference no: EM13321522

Questions Cloud

Define the concept of a servicescape or physical evidence : Question :Define the concept of a ‘servicescape’ or physical evidence. Discuss one example of a servicescape that you are familiar with. What consumer perceptions of the brand does the servicescape help to create and how?
Define dilutions for aqueous cu(no3)2 from stock : Determine how to make the following dilutions for aqueous Cu(NO3)2 from 1.0M stock : 0.50M. The 3 and 2 are both in subscript.
What is the critical path for given project : What is the critical path for this project and  how much of the total budget would be spent in Week 8 (Period 8) with the earliest start budget?
The necessary components as set forth in the rubric : Complete your Portfolio Project assignment, focusing on making sure that you have all of the necessary components as set forth in the rubric. Spend time making sure that the formatting meets APA standards, and thoroughly proofread and grammar-check y..
Minimum possible time required for completing the project : What is the minimum possible time required for completing the project and what is the latest possible time that Activity D may be started without delaying the completion of the project?
Explain transferred in galvanic cell with platinum bar : Can copper ions be transferred in galvanic cell with platinum bar. why or why not? please provide a detailed explanation
Calculate the change in potential energy of this electron : An electron is released to accelerate from point 1 to point 2 in a potential region. The electric potentials at these points are V1 = -35 V and V2 = +200 V. Calculate the change in potential energy of this electron
What is the critical path for this project : What is the minimum possible time required for completing the project and what is the latest possible time that Activity D may be started without delaying the completion of the project?
The co2 could be produced if the reaction goes to completion : CaO + C --> CaC2 + CO2 [unbalanced] If 244 g of CaO is combined with 318 g C, how many grams of CO2 could be produced if the reaction goes to completion

Reviews

Write a Review

Advanced Statistics Questions & Answers

  Relationship between speed, flow and geometry

Write a project proposal on relationship between speed, flow and geometry on single carriageway roads.

  Logistic regression model

Compute the log-odds ratio for each group in Logistic regression model.

  Logistic regression

Foundations of Logistic Regression

  Probability and statistics

The tubes produced by a machine are defective. If six tubes are inspected at random , determine the probability that.

  Solve the linear model

o This is a linear model. If your model needs a different engine, then you need to rethink your approach to the model. Remember, there are no IF, Max, or MIN statements in linear models.

  Plan the analysis

Plan the analysis

  Quantitative analysis

State the hypotheses that you are going to test.

  Modelise as a markov chain

modelise as a markov chain

  Correlation and regression

What are the degrees of freedom for regression

  Construct a frequency distribution for payment method

Construct a frequency distribution for Payment method

  Perform simple linear regression

Perform simple linear regression

  Quality control analysis

Determining the root causes

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd