Q1)

Act.} {Normal time} {Crash Time} {Normal Cost} {Crash Cost} {Immed. Pred.}
(days) (Days)
A 6 5 $900 1,000 -
B 8 6 300 400 -
C 4 3 500 600 -
D 5 3 900 1,200 A
E 8 5 1,000 1,600 C

What is the minimum cost of crashing the following project by 4 days?

Reference no: EM1339690

Questions Cloud

Expansion of american consumption : Why did American consumption expand so dramatically in the 1950s, and what aspects of society and culture did it influence?
Project scope management to success or failure of project : Why is Project Scope Management important to the success or failure of a project?
Find non quantitative factors : Simon, a second-year business student at the University of Toronto, will graduate in two years with an accounting major and a Spanish minor. Find n on-quantitative factors might Simon consider? What would you do if you were faced with these alternat..
Actions in south vietnam and us justification : What was the nation's justification for its actions in South Vietnam in the 1950s and its determination to abide by the outcome of free elections there only if those elections yielded a non-Communist leader?
Minimum cost of crashing project : What is the minimum cost of crashing the following project by 4 days?
Evaluating a business decision : Find a criteria to use in evaluating a business decision.
Explaining variable-average and total cost of production : Use GM (General Motors) as an example, explain variable, fixed, average, marginal, and total cost of production.
Practicing the policy of containment : The end of World War II brought about for many Americans an intense desire to return to normal life. It also brought about the confrontation with the Soviet Union and the beginning of the "Cold" war.
Future value and present value : Need help with the following. Can you please show me how to answer the questions at the end of this reading for future value and present value. How much will tuition and living expenses be per year when Brady is ready to attend? Give an answer for ea..

Reviews

Write a Review

Project Management Questions & Answers

  Ways in which project selection affects risk

What are some ways in which project selection affects risk? How can these risks can be reduced?

  Explaining long term costs- the impact

Explain the long term "costs" - the impact - of those choices. Then give us an overview of the corporate success measures.

  Recommending project based on estimated revenues

Would you recommend that this project be adopted? Explain why?

  Hiring project manager for most challenging projects

If you were in charge of hiring a Project Manager for one of the world's most challenging projects, what well known person would you choose to lead it and why?

  Individual part of project team as a project manager

If you were a project manager, would you want this individual as part of your project team? What will you do to get him? How should an organization cope with this situation?

  Factors to determine whether a project-s beta higher-lower

What factors determine whether a project's beta will be higher or lower when calculated against a domestic stock index versus a world stock index?

  Sequence of activities for completing the project

The time to complete a project may be shown in a chart; however, the sequence of activities for completing the project may not be shown in a chart.

  Goal of increasing capacity for passengers in hong kong area

Given the goal of increasing capacity for passengers and cargo in the Hong Kong area, what options were available?

  Developing survey to solicit input

You will develop and administer a survey to solicit input from all employees about this new system and make sure it will be user-friendly.

  Forecast the cash flows generated by project

First, Forecast the cash flows generated by project X over its economic life. Second, determine the appropriate opportunity cost of capital(r).

  Significant deficiency or material weakness

In adequate management, assertion and documentation of internal controls may result to 'significant deficiency or material weakness'.

  Determining critical path and project duration

Determine the critical path and project duration.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd