Materials quantity variance for march

Assignment Help Managerial Accounting
Reference no: EM13507274

1. Landram Corporation makes a product with the following standard costs:

  Inputs

Standard Quantity   or Hours

Standard Price or   Rate

  Direct materials

                 2.0 kilos

         $7.00 per kilo

  Direct labor

                 1.6 hours

         $14.00 per hour

  Variable overhead

                 1.6 hours

         $2.00 per hour

In March the company produced 4,600 units using 10,220 kilos of the direct material and 2,200 direct labor-hours. During the month, the company purchased 10,790 kilos of the direct material at a cost of $76,670. The actual direct labor cost was $38,246 and the actual variable overhead cost was $11,947.

The company applies variable overhead on the basis of direct labor-hours. The direct materials price variance is computed when the materials are purchased.

The materials quantity variance for March is:
A. $7,140 U
B. $7,248 U
C. $7,140 F
D. $7,248 F

2. Hurren Corporation makes a product with the following standard costs:

  Inputs

Standard Quantity or Hours

Standard Price or Rate

Standard Cost Per Unit

  Direct materials

  4.8 grams

$7.00 per gram

$33.60        

  Direct labor

  0.8 hours

$13.00 per hour

$10.40        

  Variable overhead

  0.8 hours

$8.00 per hour

$6.40        

The company reported the following results concerning this product in June.

  Originally budgeted output

6,200  

  units

  Actual output

6,100  

  units

  Raw materials used in production

28,420  

  grams

  Actual direct labor-hours

4,800  

  hours

  Purchases of raw materials

32,200  

  grams

  Actual price of raw materials purchased

$7.10  

  per gram

  Actual direct labor rate

$13.90  

  per hour

  Actual variable overhead rate

$7.70  

  per hour

The company applies variable overhead on the basis of direct labor-hours. The direct materials price variance is computed when the materials are purchased.

The labor rate variance for June is: (Round your intermediate calculations to 2 decimal places.)
A. $4,392 F
B. $4,320 F
C. $4,392 U
D. $4,320 U

3. Landram Corporation makes a product with the following standard costs:

  Inputs

Standard Quantity or Hours

Standard Price or   Rate

  Direct materials

                 2.0 kilos

           $7.00 per kilo

  Direct labor

                 1.0 hours

           $14.00 per hour

  Variable overhead

                 1.0 hours

           $6.00 per hour

In March the company produced 4,700 units using 10,280 kilos of the direct material and 2,260 direct labor-hours. During the month, the company purchased 10,850 kilos of the direct material at a cost of $76,730. The actual direct labor cost was $38,238 and the actual variable overhead cost was $11,939.
The company applies variable overhead on the basis of direct labor-hours. The direct materials price variance is computed when the materials are purchased.

The materials price variance for March is: (Do not round intermediate calculations.)
A. $640 U
B. $780 F
C. $780 U
D. $640 F

Reference no: EM13507274

Questions Cloud

Identifying a key marketing related business challenge : 1. Identifying a key marketing related business challenge within the organisation that the student works for or has frequent dealings
Identify the most important facts about the diet : Analyze your own protein intake. You should collect, organize, and report data related to your own protein requirements. For your analysis, you should
Compute the total asset turnover rate : Compute the total asset turnover rate assuming that total revenues in 2012 were $682,500. Round to the nearest hundredth, e.g. 3.33.
Would it include a debit to depreciation expense : Sky Company collected $12,350 in interest during 2013. Sky showed $1,850 in interest receivable on its December 31, 2013, balance sheet and $5,300 on December 31, 2012.
Materials quantity variance for march : The company applies variable overhead on the basis of direct labor-hours. The direct materials price variance is computed when the materials are purchased.
Managing a small cross-functional project team : Managing a small cross-functional project team
Determine the heat transfer for the process : One kilogram of water vapor (as an ideal gas) is filled in a frictionless piston-cylinder assembly. The piston can move freely in the cylinder and it is in surroundings of 1 atm. Determine the heat transfer for the process
Determine the optimal quantities of the decision variables : Determine the optimal quantities of the decision variables.
Explain the cycle and the overall cycle : A sample consisting of 1.45 mol of perfect gas atoms is taken through the following cycle: step1 constant pressure, change in volume from 22.44L to 44.88L. Step2 Constant volume, change pressure from 1bar to .35bar.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd