The cost sheet of Sarvesh Led. Provides the following data:
Amount per unit (Rs.)
Raw materials 100
Direct labour 40
Overheads 80
Selling price 240
The following is the additional information:
Level of activity 1,04,000 units p.a.
Raw materials in stock average 4 weeks
Work-in-progress average 2 weeks
Finished goods in stock average 3 weeks
Credit allowed by suppliers 1month
Credit allowed to customers 3 weeks
Lag in payment of wages 2 weeks
Minimum cash balance of Rs. 20,000 is to be maintained. Production is carried on evenly throughout the year. A safety margin of 10% will be maintained.
Question 1: You are required to a statement showing working capital requirements of Sarvesh Ltd.