Consider a project having the following six activities:

Immediate                                                                

              Activity                                  Predecessors            Time (weeks)                      

                      A                                       none                                          7                                            

                      B                                       none                                          3                                            

                      C                                         A                                               5                                            

                      D                                      A, B                                            6                                            

                      E                                       C, D                                            4                                            

                      F                                         D                                               3

 

1. Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task.

2. List the tasks on the critical path

3. What is the expected project duration in weeks?

4. What is the slack for each activity?

A: B: C: D: E: F:

Reference no: EM13792610

Questions Cloud

Describe the purpose and operating principles : Describe the purpose and operating principles of typical flight instruments. For primary flight instruments, give examples of redundancy and correctly interpret flight instrument indications. Write a four page paper APA style with references
Problems of periodization and its components : Explain this belief, evaluate it and tell why it may or may not be appropriate. Are there other ways to burn fat? If so, what are some of them?
Define models for strategic planning formulation : Write a report applying two models for strategic planning formulation. You may choose to report on the feasibility of a business you want to start
Explain what these risk and protective factors : Explain what these risk and protective factors
List the tasks on the critical path : Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task.
Union workers in the public sector : Benefits and supplemental pay accounted for 50 percent of compensation costs for civilian workers as of June 2011
Describe the leadership perspectives : Which of the leadership perspectives do you think is manifested in both coaches? What are the power bases both coaches rely upon. Whose actions are more aligned with a managerial role and whose actions are more aligned with a leadership role
Definition and an example of sodality : 1. Provide a definition and an example of sodality. 2. Define and elaborate upon the concept of pan-tribal sodality.
Income tax or filed a tax return : Mr. T has not paid income tax or filed a tax return for the last eight years. He believes that the IRS can no longer assess any back taxes for the first five of those years.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd