Reference no: EM133055830
BUS407 Project Management - Emirates College of Technology
Project Task
You have to respect the working guidelines given below and the submission date stated on the LMS.
Working Guidelines for Project
A. Project Structure:
It is recommended that your project report have the following structure in the order provided here.
Title page
The students' details should be filled in the cover letter provided.
Abstract / Executive Summary
The Abstract consists of the project title and about half a page concise summary containing the scope and results of your report.
Table of Contents
Table of contents should contain titles and page numbers for the main sections and subsections of your report. The table of contents should also include any appendices in your report.
Report Body For each question need to write title (heading) from the question itself before writing the answer (don't write question copy paste)
This is the central and main part of the project which contains the actual work done during the project. The main requirement is that you need to structure the report so that it is clear and structured in a way that makes sense. Grammar and spellings count.
Conclusions
The project's conclusions should list the things which have been learnt as a result of the work you have done.
References
You are responsible for appropriately citing material and methods that you use. Give references for the data collected from a textbook, a magazine or a website identifying its sources while using the appropriate form. In the references section, references should be in a numbered list, ordered alphabetically by the last name of the first author.
Project ideas: Career Fair (Job Fair)
at the Emirates College of Technology
Project Details: Need to assume about the project idea given title and answers the 8 questions required follow by the guidelines for project structures.
Project idea: Career Fair (Job Fair) at the Emirates College of Technology
Identify the project type
Clarify the project idea and its objective through the scope statement and statement of work.
List and define the activities of the project (7-12 activities).
Activity Description Immediate Predecessor Activity Time : T
State the dependency between the project activities and the duration (To, Tm, Tp, Te) for each activity.
Note: you have to state (To, Tm, Tp, Te) like attached example before table to know how you got the answer when you calculate each durations
Activity IPA Duration Expected time (Te)
Draw the project network diagram (A-O-N method).
Note: the number beside each activity is the Activity Time : T (in days) not Expected time
Like below ways & draw like second example (blue example) here (not capture photo or hand draw):
Note: For below questions 7 & 8 see the handout attached from slide 53 till 65 and do similar way of the steps of solving the example their.
List the critical path(s) in the project and the project duration
Note: List the critical path(s) in the project and the project duration then choose the longest taking days (see example attached)
calculate the slack time and the possibility to finish early.