Linear programming-production problem

Assignment Help Operation Management
Reference no: EM13812715

Linear Programming: Production Problem

A manufacturing company produces four different models of integrated circuits. Each type of circuit requires material, labor, and machine time. The optimal combination of the four types of circuits is limited by the constraints of availability for these three resources. The formulation of the linear programming production problem is:

Maximize Z = 12x1 + 10x2 + 15x3 + 11x4 (objective function for profit)

Subject to the following constraints:

Material: 5x1 + 3x2 + 4x3 + 2x4 <= 240 pounds
Machine time: 6x1 + 8x2 + 2x3 + 3x4 <= 240 hours
Labor: 2x1 + 3x2 + 3x3 + 2x<= 180 hours

Nonnegativity: x1, x2, x3, x4 >= 0

Where: x1 = quantity of Product 1 produced

  • x2 = quantity of Product 2 produced
  • x3 = quantity of Product 3 produced
  • x4 = quantity of Product 4 produced

Use Microsoft Excel and Solver to find the optimal solution for the production problem. Be sure that values selected by the computer are integers (as it doesn't make any sense to discuss producing part of a unit of a product).

Include your interpretation of the results by stating:

  • How many of each product will be produced?
  • What is the profit for the optimal solution?
  • What resource(s) is limiting the production?

Reference no: EM13812715

Questions Cloud

Developing an online database : When a member logs onto the database, all session information, such as IP address, terminal, and user session information, must be recorded for future analysis.
Project without changing the network diagram : Project crashing expedites the project without changing the network diagram. Another approach to expediting the project is called fast tracking, which means converting some sequential activities to parallel activities.
Write a review of the given article : Read the article When in Rome...: Influences on Special Education Student-Teachers' Teaching by Lysandra Cook. Then write a review of the above article.
Nature of the objective function : What would be the nature of the objective function in such an environment? What types of constraints would exist on the number of camels and number of dromedaries?
Linear programming-production problem : A manufacturing company produces four different models of integrated circuits. Each type of circuit requires material, labor, and machine time. The optimal combination of the four types of circuits is limited by the constraints of availability for..
Commercialization of organ transplants : Commercialization of Organ Transplants
How does the figurative language help poem communicate to us : Show a few examples of figurative language at work. How does the figurative language you have chosen help the poem communicate to us as readers?
Sociology research paper on american families : Sociology Research Paper-American Families
What are the flaking methods used by early people : What are the flaking methods used by early people during paleolithic with specific examples

Reviews

Write a Review

Operation Management Questions & Answers

  Draw the product structure tree

Draw the product structure tree if 30 units ofA are required in Week 8, determine the necessary planned order releases for all components

  Which method provides a lower total cost

If the company produces 1,173 tables a year, which method provides a lower total cost? Process 1 Process 2.

  What are the main types of political risk

What are the main types of political risk? How might each affect international business activity

  Synergy is an often-used word in business

Synergy is an often-used word in business

  Describe customer contact matrix perspective

Describe a company of your choice from the customer-contact matrix perspective. Discuss the operations of the organization from your perspective using the three elements of the customer-contact matrix.

  If the firm employs the continuous review system to control

a store has collected the following information on one of its productsdemand 15000 unitsyearstandard deviation of

  What are the four types of resource constraints

What are the four types of resource constraints? Please list them and provide an example of each.

  What is the resulting year 2014 forecast value

Using this data and a smoothing constant alpha of 0.5, what is the resulting year 2014 forecast value?

  Main problem with performance appraisal

The main problem with performance appraisal programs is supervisory bias when making judgments. How can a company attempt to identify and reduce appraisal bias? Respond substantively to two other learners.

  Alternative one reduces wasted motion

Alternative One reduces wasted motion (walking) to 1% of total labor used on the assembly line. Physical lifting is reduced to no more then 12 pounds. Six people will be required on the assembly line. Productivity in finished goods per 8-hour shif..

  How you handle distribution and marketing of the o-fold

As a part of the management team, how would you handle distribution and marketing of the O-Fold?

  Write down a 700- to 1400-word paper explaining the laws

write a 700- to 1400-word paper describing the laws governing legal authority and licensing requirements for private

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd