Life and death of an aircraft development project

Assignment Help Operation Management
Reference no: EM131479231

Life and Death of an Aircraft Development Project

Law and Callon described the history of a large British aerospace project in terms of two entities: the global system and the project itself. The global system comprised parties and organizations outside the project that had a stake in the project; the project comprised everything within the project including all work and the organizations contracted to do it.

THE GLOBAL SYSTEM

The principal stakeholders in the global system were: 1. The Royal Air Force (RAF), which initiated the project with a request for a new supersonic aircraft with short take-off capability. The aircraft would be a “tactical strike and reconnaissance fighter” called TSR. 2. The Ministry of Defence (MOD), which wanted an aircraft that would best fit the nation’s current overall defense needs. 3. The Treasury, which wanted an inexpensive aircraft that would have market appeal for sale outside the UK, such as to the Royal Australian Air Force (RAAF). 4. The Royal Navy (RN), which wanted to buy a different aircraft but was under pressure by MOD to buy the TSR. 5. The Ministry of Supply (MOS), which wanted an aircraft that would be produced by a consortium of several UK airframe and engine manufacturers. As is typical of most projects, each stakeholder in the global system conceptualized the project differently: to the RAF and MOD it would yield an aircraft for a specific mission; to the Treasury it would fit the defense budget and generate revenue; to the RN it was a competitive threat to the aircraft they really wanted; and to the MOS it was an instrument of industrial policy. The parties had different reasons for contributing resources and support: some were economic (in return for funds, an aircraft would be built); some political (in return for a demonstrated need, objections of the RN would be overruled); some technical (in return for engineering and technical effort, the aircraft would meet RAF performance requirements); and some industrial (in exchange for contracts, the aircraft industry would be consolidated).

THE PROJECT

The Treasury would not approve project funding until the aircraft’s basic design, manufacturer, cost, and delivery date were defined. The RAF and MOD sent requests to the aircraft industry for design ideas, and selected two manufacturers: Vickers Corp. and English Electric (EE). They favored Vickers for its integration capability (combining aircraft, engine, armaments, and support equipment into a single weapons package), but they also liked EE for its design experience with supersonic aircraft. So they decided to contract with both companies and adopt a design that would utilize features from both. The idea was approved by all other parties in the global system, and funding for the project was released. The project grew as Vickers and EE hired subcontractors and expanded their teams for design, production, and management. The two companies and several other contractors merged to form a single new organization called the British Aircraft Corporation (BAC).

RELATIONSHIPS BETWEEN THE GLOBAL SYSTEM AND THE PROJECT

As the project grew, so did the problems between it and the global system. The MOS wanted centralized control over all aspects of the project, and all transactions between the project and stakeholders in the global system. Although BAC was the prime contractor and ostensibly responsible for managing the project, the MOS would not confer upon it the necessary management authority. Rather, the MOS formed a series of committees with members from the global system and gave them primary responsibility to manage the project. This led to serious problems: 1. The committees were allowed to make or veto important project-related decisions. They, not BAC, awarded important contracts; when the RAF wanted to change its requirements, it consulted with the committees, not with BAC. 2. The committees often lacked sufficient information or knowledge. Technical committees made decisions without regard to costs; cost committees made decisions without regard to technical realities. Decisions focused on particular aspects of the project; seldom did they account for impacts on other parts of the project, or the project as a whole. Distrust grew between BAC and the MOS; neither was able to effectively integrate the resources, information, and decisions flowing between parties in the project and the global system. Subcontractors became difficult to control. Many ignored BAC and worked only with the MOS and RAF to get favorable treatment.

GLOBAL SYSTEM RESHAPED

Everyone knew the project was in trouble. Project costs doubled. One of the test engines exploded, and the RAF recognized it might take years to understand the cause. In addition, the RAAF announced that it would not order the TSR but was instead buying the US-built F-111. Opposition to the project grew, and in the upcoming general election the Labour Party promised that if elected it would review the project. When the Labour Party won, it immediately began an assessment of the project, which included comparing the TSR to the F-111—considered by now an alternative to the TSR. As cost overruns and schedule delays continued, the MOS slowly withdrew support. The RAF then withdrew its support, when it discovered that the F-111, which was already in production, would meet all of its requirements. The project was canceled.

QUESTIONS

1. In this case history, what is the “system” and what are its elements? What is the “environment,” and what are the elements of the environment?

2. Describe the interaction between the system and its environment.

3. Do you feel that important decisions made in this project represent “system thinking”? Explain.

4. Comment on the concept of “integration” in the project. How were aspects of the project integrated or not integrated?

5. What are the main factors that contributed to cancellation of the project? Which of these factors would you characterize as project management?

Reference no: EM131479231

Questions Cloud

Diseases affecting children than diseases affecting elderly : The Health Bureau of a state government decides to provide more funding to resolve diseases affecting children than diseases affecting the elderly.
In making a decision on land-use in suburban area : In making a decision on land-use in a suburban area, the county government resolves to avoid giving special treatment to any particular interest groups.
Account when carrying out a benefit-cost analysis : Which of the following is not a factor that needs to be taken into account when carrying out a benefit-cost analysis?
Perspective of swot analysis : From the perspective of SWOT analysis, which of the following is a threat?
Life and death of an aircraft development project : Law and Callon described the history of a large British aerospace project in terms of two entities: Describe interaction between the system and its environment.
How the psychological traits of individuals influences : What psychological sub-discipline examines how the psychological traits of individuals influences how they make decisions?
Examining carefully the decision space of decision : Which of the following is an important benefit associated with examining carefully the decision space of a decision?
How inter-organizational and intra-organizational systems : Explain how the inter-organizational and intra-organizational systems play a role in reducing the cycle and lead time?
How supply chains are structured-logistics innovation : Explain how supply chains are structured and also discuss logistics innovation.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd