Learning curve-roduced for the first unit of item

Assignment Help Operation Management
Reference no: EM131133353

A skilled worker, believed to be on a 90% Learning Curve, produced for the first unit of the item no X235 in 75 minutes. According to your calculations, the same worker should be able to produce the unit # 12 of X235 in approximately:

a. 49 minutes b. 75 minutes c. 51 minutes d. 31 minutes

Reference no: EM131133353

Questions Cloud

Super discount overbook the flight : Next week, Super Discount Airlines has a flight from New York to Los Angeles that will be booked to capacity. The airline knows from past history that an average of 25 customers (with a standard deviation of 13) cancel their reservation or do not sho..
Durable medical equipment subsidiary : You are outside counsel to the Marcus Welby Healthcare Corporation, which among its other operations owns a durable medical equipment (DME) subsidiary, which sells equipment for home use such as crutches, wheelchairs, and oxygen concentrators. The su..
Business and risk-sharing objectives : How does air cargo differ from the passenger business in terms of revenue management? Which areas are more complex, and which can be managed more easily? What is the purpose of selling long-tem capacity contracts? Does Lufthansa Cargo effectively rea..
Lettuce should the supermarket purchase tomorrow : The local supermarket buys lettuce each day to ensure really fresh produce. Each morning any lettuce that is left from the previous day is sold to a dealer that resells it to farmers who use it to feed their animals. How many boxes of lettuce should ..
Learning curve-roduced for the first unit of item : A skilled worker, believed to be on a 90% Learning Curve, produced for the first unit of the item no X235 in 75 minutes. According to your calculations, the same worker should be able to produce the unit # 12 of X235 in approximately:
Time estimates-optimistic time : A PERT Activity has the following three time estimates: Optimistic Time (a)= 12 weeks Pessimistic time (b)= 24 Weeks Most Likely Time (m)= 15 The expected completion time (te+/- SD) for this activity is: a. 17+/-4 b. 16+/-4 c. 18+/-2 d. 16+/-2 Weeks
Create your own linear programming problem : Create your own Linear Programming problem: State the problem, with at least 3 decision variables and constraints. Solve using Simplex & analysis of the solution and recommendation; what do you see and what could be done?
What is average outgoing quality : Suppose that only two incoming fraction defective levels, 4 percent and 8 percent, are possible. These incoming fraction defective levels are equally likely. At a 4 percent incoming fraction defective, there's a 60 percent chance that a lot will be a..
Identify the reporting elements and levels : The project start-up phase is complete, and you are now ready to finalize the operational plan. Below are six steps that are often part of the finalization procedure. Place them in the appropriate order. Establish the work breakdown structure and ide..

Reviews

Write a Review

Operation Management Questions & Answers

  Managerial skills-management levels in the organization

Which managerial skills often determine who reaches the highest management levels in the organization?

  Draft a memo explaining to your warehouse managers

Draft a memo explaining to your warehouse managers how effective supply chain design could help to enhance profitability and stakeholder value for the company, including the following:

  Increased standards of living and affordable products

What is credited with gains in industrial productivity, increased standards of living and affordable products?

  Total associate costs-expected time customer is in system

Money R’Us is an all-purpose financial institution located in Dayton’s financial district. Money R’Us has 6 departments and a supervisory staff as shown below. Customers arrive at each department at random (i.e. a Poisson process) with mean arrival r..

  Writenbsp down a short essay which explains e-supply chain

1. define the term e-business. 2. define supply chain and list the activities that are involved. 3. write a short essay

  Define managerial epidemiology

In your own words, define managerial epidemiology and address the significance of using epidemiology principles and tools while making administrative decisions.

  Product process matrix for analysis

Product Process Matrix For Analysis

  Evaluate the success of the company

Evaluate the success of the company in reacting to an external change and analyze how this reaction impacted the company's performance

  The optimal quantities of products and the necessary

Prepare a report that addresses the following issues: The optimal quantities of products and the necessary quantities of labor and materials.

  Calculate the profit each year using variable costing

Sterling Corporation reports the following information: 2009 2010 2011 Units sold 20,000 20,000 20,000 Units produced 20,000 24,000 16,000 Fixed production costs $1,200,000 $1,200,000 $1,200,000 Variable production costs per unit $200 $200 $200 Selli..

  Identify opportunities to enhance data-analytics efforts

List the human capital and infrastructure needed to implement data sharing solutions. Include hardware, software, and Cloud storage solutions. Identify opportunities to enhance data-analytics efforts and capabilities.

  What is the average number of cars in the system

What is the average number of cars in the system (both in line and at the window)? Do not round intermediate calculations. Round to 2 deceimal places.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd