King Manufacturing has four categories of overhead. The four categories and expected overhead costs for each category for next year are as follows:

Maintenance

$70,000

Materials handling

30,000

Setups

25,000

Inspection

50,000

Currently, overhead is applied using a predetermined overhead rate based upon budgeted direct labor hours. 50,000 direct labor hours are budgeted for next year.

The company has been asked to submit a bid for a proposed job. The plant manager feels that obtaining this job would result in new business in future years. Usually, bids are based upon full manufacturing cost plus 30 percent.

Estimates for the proposed job are as follows:

Direct materials

$2,500

Direct labor (750 hours)

$3,750

Number of machine hours

300

Number of material moves

8

Number of setups

3

Number of inspections

5

In the past, full manufacturing cost has been calculated by allocating overhead using a volume-based driver e.g. direct labor hours. The plant manager has heard of a new way of applying overhead that uses cost pools and activity drivers.

Expected activity for the four activity drivers that would be used are:

Machine hours

16,000

Material moves

4,000

Setups

2,000

Quality inspections

8,000

Required:

  1. Determine the company's bid if direct labor hours are used as the volume-based driver and the bid is based upon full manufacturing cost plus 30 percent.
  2. Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.
  3. Which product costing method produces the more competitive bid? And why?

Problem :- 2

The Knapp Company needs to predict the labor cost in producing small carrot patch dolls. The following production information is available:

Year

Dolls Produced

Labor Hours

Labor Dollars

2005

1,150

 850

$17,000 

2006

1,600

 975

23,400

2007

1,100

 800

25,600

2008

2,100

1,150 

36,800

2009

1,500

 950

34,200

2010

1,300

 875

35,000

The technology has not changed since 2005. Wage rates have steadily increased since 2005; however, management expects no further wage increases in 2011.

Required:

  1. Select the appropriate independent variable for predicting labor cost. Explain the reason for your selection.
  2. Develop an equation to predict for 2011 the labor cost of producing carrot patch dolls. Use the high-low method.
  3. Estimate the labor cost of producing 3000 carrot patch dolls for 2011 if 3,000 dolls are expected to produce.

Reference no: EM13346500

Questions Cloud

Provide an executive summary of the individual researchwhat : provide an executive summary of the individual research.what were the key conclusions of the research?identify what you
Andrew brian colin diana and elizabeth were the directors : andrew brian colin diana and elizabeth were the directors of gemsales pty ltd a company engaged in the business of
Each candidate in this class is to identify a teacher in : each candidate in this class is to identify a teacher in herhis school who is willing to participate in a supervisory
Write a report on change is the only constant and answer : write a report on change is the only constant and answer the subsequent questions.1. change is the only constant
King manufacturing has four categories of overhead the four : king manufacturing has four categories of overhead. the four categories and expected overhead costs for each category
The basic requirement is the preparation of a financial : the basic requirement is the preparation of a financial report that provides specific advice for client.jossiah and
Sturdivant sound systems manufactures and sells sound : sturdivant sound systems manufactures and sells sound systems for both home and audio. all parts of the sound systems
1 bart agrees to put sams super bowl champion-ship : 1. bart agrees to put sams super bowl champion-ship autographed football in his sports store to sell for 1500. sam
With current technology consider a firm is producing 400 : with current technology consider a firm is producing 400 loaves of bread daily. suppose that the least cost combination

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd