IT Project Management Calculations

Assume you have completed three months of the project. The BAC was $200 000 for this six month project. Also assume the following:

PV = $120,000
EV = $100,000
AC = $90,000

A. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

B. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

C. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

Reference no: EM13363393

Questions Cloud

Systematic risk and unsystematic risk beta coefficientwhat : systematic risk and unsystematic risk beta coefficientwhat is the difference between systematic risk and unsystematic
Solution to free cash flowanalysts expect a project to : solution to free cash flowanalysts expect a project to generate ebit of 500000 per year for 5 years. depreciation
What are some techniques to speed up a project and under : what are some techniques to speed up a project and under what circumstances might they be implemented? is hiringadding
Describe project risk management as a component of the : describe project risk management as a component of the project management processyou met with the entire project team
It project management calculationsassume you have completed : it project management calculationsassume you have completed three months of the project. the bac was 200 000 for this
Conjoint analysisthere are only six modules so the timeline : conjoint analysisthere are only six modules so the timeline would be for the completion. thank you.1. a completed copy
Project managementcompany a works in a business environment : project managementcompany a works in a business environment of rapid and drastic change together with strong
Project analysis explainedyour company decides to buy the : project analysis explainedyour company decides to buy the new equipment to replace the existing equipment. for
Project evaluation explained in this answerthe company : project evaluation explained in this answerthe company decides to buy the new equipment to replace the existing

Reviews

Write a Review

Project Management Questions & Answers

  Determining sales contracts

Provide a well written answer of not less than 200 words to the following. Weaver Mills Co. in Country F contracted to purchase 100,000 yards of jute from Natural Fiber Co. in Country G at US$ 0.64 per yard. Natural delivered 22,228 yards

  Show the knowledge of the sdlc

What's the appropriate level and kinds of advice about the Systems Development Life Cycle are appropriate to give to the aspiring Project manager?

  Describe why social media is important to the firm

Describe why social media is important to the firm and clarify the social media's goals and provide details about how to handle common situations such as negative complaints or scandals.

  Benefits of developing using dashboard

The benefits of developing and using the dashboard in your organization.

  The main purpose of aggregate operations planning

The main purpose of aggregate operations planning is to specify the optimal combination of which of the following?

  Calculate the slack associated in the given casegiven this

calculate the slack associated in the given casegiven this information about an activity es 10 ef 15 ls 26 and lf

  Joe has worked for blanque cheque construction bcc for five

joe has worked for blanque cheque construction bcc for five years mainly in administrative positions. three months ago

  Speculating the deliverables of the project

Also, speculate the deliverables you would provide if you are working on the project.

  Discussing project schedule and its next steps

Then, you would like to schedule an emergency meeting with her and the other marketing department managers to discuss the project schedule and next steps.

  Explain the process of subdivision of activities

Explain the process of subdivision of activities and events that composes the tree diagram known as the Work Breakdown Structure.

  1what percentage of the total project effort do you think

1.what percentage of the total project effort do you think should be devoted to planning? why?2. explain the process of

  Project costs analyzing a project trade off

What are the possible project costs that need to be considered when analyzing a project trade off?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd