Reference no: EM131104540
Reconsider Prob. 10.4-3, which involves trying to find the probability that a project will be completed by the deadline. Assume now that the duration of each activity has a triangular distribution that is based on the three estimates in the manner depicted in Fig. 22.10. Obtain a close estimate of the probability of meeting the deadline by performing 1,000 iterations of a simulation of the project on a spreadsheet. Generate the various available kinds of outputs similar to Fig. 22.12.
Prob. 10.4-3
Reconsider Prob. 10.4-2. For each of the 10 activities, here are the three estimates that led to the estimates of the mean and variance of the duration of the activity (rounded to the nearest integer) given in the table for Prob. 10.4-2.

(Note how the great uncertainty in the duration of these research activities causes each pessimistic estimate to be several times larger than either the optimistic estimate or the most likely estimate.) Now use the Excel template in your OR Courseware (as depicted in Fig. 10.10) to help you carry out the instructions for Prob. 10.4-2. In particular, enter the three estimates for each activity, and the template immediately will display the estimates of the means and variances of the activity durations. After indicating each path of interest, the template also will display the approximate probability that the path will be completed within 22 months
Prob. 10.4-2
Alfred Lowenstein is the president of the research division for Better Health, Inc., a major pharmaceutical company. His most important project coming up is the development of a new drug to combat AIDS. He has identified 10 groups in his division which will need to carry out different phases of this research and development project. Referring to the work to be done by the respective groups as activities A, B, . . . , J, the precedence relationships for when these groups need to do their work are shown in the following project network.


(a) Find the mean critical path for this project.
(b) Use this mean critical path to find the approximate probability that the project will be completed within 22 months.
(c) Now consider the other three paths through this project network. For each of these paths, find the approximate probability that the path will be completed within 22 months.
(d) What should Alfred tell his CEO about the likelihood that the drug will be ready within 22 months?

Fig. 22.12

Employee health insurance experience on a spreadsheet
: Look ahead at the scenario described in. Obtain a close estimate of the expected cost of insurance coverage for the corporation's employees by performing 500 iterations of a simulation of an employee's health insurance experience on a spreadsheet.
|
Java class that represents your favorite musical instrument
: Create your own Java class that represents your favorite musical instrument. Your musical instrument class should have at least 3 constants, 5 private data fields, getters and setters for each private data field, a to String() method, and three ad..
|
Ridership demand with the increase
: A bus traveling on the HOT lane currently charges $1.50 and has 100,000 riders per day. The transit agency is planning to raise fares to $2.00 and knows that the price elasticity for the bus is -0.21. What is the expected change in ridership deman..
|
Federov corporation has eight expense accounts
: Should Federov report these eight expenses separately in its income statement or simply report one total amount for selling expenses?
|
Involves trying to find the probability that a project
: Reconsider Prob. 10.4-3, which involves trying to find the probability that a project will be completed by the deadline. Assume now that the duration of each activity has a triangular distribution that is based on the three estimates in the manner..
|
Business practices in the future
: What new technologies do you find most fascinating? How might they effect business practices in the future?
|
What would be your provisional diagnosis of laurel
: A description of the steps you will take to build rapport with Laurel and help her feel comfortable in confiding in you. Consider the work of Carl Rogers Person Centered Theory; the work of Insoo Kim Berg Solution-Focused Brief Theory (SFBT); and ..
|
Write an analysis of the ten technology initiatives
: In a three- to five-page paper (not including the title and reference pages), write an analysis of each of the ten technology initiatives and, using scholarly research, provide a practical example of each initiative.
|
Particular set of people who bank
: The data will only apply to these people, whereas it would have been better to have a broader set of people to use. for eg, it is important to include those who don't visit a bank frequently to target them. We are already confining ourselves to a..
|