Inventory decision making and eoq concepts

Assignment Help Business Management
Reference no: EM134619

Queston 11

Gemini Fabricators

(This case deals with inventory decision making and EOQ concepts.)

Gemini Fabricators produces parts and subassemblies for a number of small-volume manufacturers of specialized construction equipment, including bulldozers, graders, and cement mixers. Gemini also manufactures and distributes spare parts. The company has made a specialty of providing spare parts and replacement parts for equipment no longer in production by the original equipment manufacturers.

The Materials Management Group (MMG) orders parts - both for delivery to a customer's production line and for spares - from the Fabrication Department. Spares are stocked in a Finished Goods Store. Gemini's part number 650810/ss/R9/o is a wear part made only for spares demand. It has had demand averaging 300 units per week for more than a year, and this level of demand is expected to persist in the foreseeable future.

The MMG has been ordering 2600 units every other month for part number 650810/ss/R9/o from the Fabrication Department to meet the forecast annual demand of 15,600 units. The order is placed at the beginning of every other month. In order to provide Fabrication with scheduling flexibility, as well as to help with planning raw material requirements, a 2-week manufacturing lead time is allowed for parts.

In the Fabrication Department, 3 hours is now allowed for each setup for a run of part number 650810/ss/R9/o. This time includes strip-down of the previous setup; delivery of raw materials, drawings, tools and fixtures, etc; and buildup of the new setup. The 3-hour setup time is a recent improvement over the previous 4 hours, as the result of setup reduction activities in the Fabrication Department. The Fabrication Department charges $35 per hour for setups. Part number 650810/ss/R9/o enters the Finished Goods Stores at a full manufacturing cost of $40.44. The Financial Office has indicated a 10% per unit per year holding cost (based on its full manufacturing cost).

Case Questions

1) What is the total annual cost of the present ordering policy for part number 650810/ss/R9/o?

2) What would be the lot size for part number 650810/ss/R9/o if Gemini were to use an economic order quantity (EOQ)?

3) How often would Gemini be ordering part number 650810/ss/R9/o if they were to use the EOQ?

4) What would be the total annual cost of using an economic order quantity for part number 650810/ss/R9/o?

5) What would the annual cost savings be if Gemini were to utilize an EOQ approach to ordering rather than the current policy of ordering 2600 units in each replenishment?

6) Presumptuous that the 300 units per week demand for part number 650810/ss/R9/o is fairly uniform, what would the rearrange point be for this item?

Reference no: EM134619

Questions Cloud

Main elements of the system requirements document : Susan has been requested to prepare a system requirements document as well as deliver a presentation to the management team. What must be the main elements of the system requirements document
What was the average acceleration throughout the trip : What was the average acceleration throughout the trip
Decisive influences on strategy formulation : Decisive Influences on Strategy Formulation
What are direction and magnitude of total velocity : What are direction and magnitude of total velocity
Inventory decision making and eoq concepts : inventory decision making and EOQ concepts
Business process improvement : How does the Tata Business Excellence Model differentiate between levels of maturity?
Find out the potential difference between r2 and r1 : Find out the potential difference between r2 and r1
Liquidates the entire inventory : Assuming that Attic's awareness stays the same next year (77%), out of the promotion budgets below, what is the minimum Chester's Elite product manager must spend in promotion to earn more awareness than Andrews' Attic product?
What is an initial speed given to the rock : What is an initial speed given to the rock

Reviews

Write a Review

Business Management Questions & Answers

  Develop the gratified for the second half of the training

Develop the gratified for the second half of the training program Write a 2-page novel case study in which you present a scenario (related to some aspect of employment law) for trainees to analyze. The scenario may be theoretical or based on act..

  Meaning of behaviour-based safety programmes enumerating

Describe briefly the meaning of Behaviour-Based Safety Programmes enumerating the features of these programmes Elaborate on the ways of controlling risks at worksite as per the Hierarchy of Control

  Structure of business plan

This assignment shows a structure of business plan. The task is to write a business plane about a Diet Shop.

  What is the project''s mirr

The firm's management is uncomfortable with the IRR reinvestment assumption and prefers the modified IRR approach. You have calculated a cost of capital for the firm of 12%. What is the project's MIRR?

  Labour used in production

All of the subsequent are physical resources EXCEPT • Raw materials • A robotic welder • Labour used in production • An inventory of finished goods • An office building

  What are the benefits to good communication

What are the benefits to good communication

  Prepare an income statement

Prepare an income statement for the year

  What laws have been disrupt

What laws have been disrupt here if any, What are Gant's damages? Are there any additional facts that we require to find out in order to resolve this dispute.

  What are the potential benefits of each stage

Why an ERP systems journey may never end What are the possible stages in an ERP systems journey? What are the potential benefits of each stage?

  Is there a stated policy with definite principles

Is there a stated policy with definite principles for writing off obsolete or slow-moving goods

  Analyze accountable actions

Can Karen effectively sue for false imprisonment or defamation? From what you have erudite about the relationship between a principal and an agent, analyze whether Steve or Big Mart could be accountable because of Steve's actions.

  Concept the sequential game tree by business organization

Concept the sequential game tree when Samsung makes the first change by deciding whether to invest in extra production capacity

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd