Consider the following operation elements required to hang insulation on a metal surface inside a ship machinery space:
Grab stud gun, shoot 5 pins on bulkhead
Return gun to scaffold, grab insulation square and press into pins
Grab cutting tool from belt and trim insulation square with bulkhead frame.
Return cutting tool to belt, grab seam tape and apply to joint
Grab paint marker, inspect installation and write current date and initials on panel.
Develop a personal delay and fatigue allowance factor using the ILO Recommended allowances from your text for the elements. Include constant and variable allowances. Assume that all the elements are subject to same conditions:
Work is done while standing at all times
Position is awkward at all times
Use of force and muscular energy is negligible
Lighting is “well below” the recommended lumen level for this task
Heat humidity are not a factor due to ventilation in the work space.
The tasks are “fairly fine work”, which does not require much attention to detail.
Noise level is intermittent and loud
Monotony and tediousness are both at the medium (b) level.
In the field provided, type your total allowance, showing the individual components that you used to develop the value.