Information to develop a project network

Assignment Help Project Management
Reference no: EM13928781

1. Information to develop a project network is collected from the

A. Organization breakdown structure
B. Work breakdown structure
C. Budget
D. Project proposal
E. Responsibility matrix

2. Which of the following represents an activity on an AON project network?

A. An arrow
B. A line
C. A node
D. Both A and B are correct
E. A, B, and C are all correct

3. Arrows on an AON project network represent:

A. An activity
B. Project flow
C. Dependency
D. Both B and C are correct
E. Both A and B are correct

4. When translated into a project network, a work package will become

A. A single activity
B. One or more activities
C. A milestone
D. A critical path
E. An arrow

5. Which of the following is provided by a project network but not by the work breakdown structure?

A. Dependencies
B. Sequencing
C. Interrelationships
D. Both A and B are correct
E. A, B, and C are all correct

6. On a project network, the activity times are derived from the

A. Organization breakdown structure
B. Work packages
C. Budget
D. Project proposal
E. Responsibility matrix

7. Part of a project is to Develop Product Specifications. This is best classified as a(n)

A. Event
B. Path
C. Activity
D. Node
E. Milestone

8. An activity that has more than one dependency arrow flowing into it is termed a(n)

A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

9. The critical path in a project network is the

A. Shortest path through the network
B. Longest path through the network
C. Network path with the most difficult activities
D. Network path using the most resources
E. Network path with the most merge activities

10. A/an _________ activity has more than one dependency arrow flowing from it.

A. Parallel
B. Critical path
C. Burst
D. Merge
E. Independent

11. An item on a project network is Design Software Completed. This is best described as a(n)

A. Event
B. Path
C. Activity
D. Node
E. Milestone

12. Activities which can take place at the same time are termed

A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

13. A sequence of connected, dependent activities is termed a(n)

A. Critical path
B. Parallel path
C. Activity chain
D. Path
E. Dependent chain

14. An AON project network uses which of the following basic building blocks?

A. Arrows
B. Bars
C. Nodes
D. Both A and C are correct
E. A, B, and C are all correct

15. Which of the following is not one of the basic rules to follow when developing project networks?

A. An activity cannot begin until all preceding activities have been completed
B. Each activity must have a unique identification number
C. Conditional statements are allowed but looping statements are not allowed
D. An activity identification number must be larger that that of any preceding activities
E. Networks flow from left to right

16. ________ activities must be completed immediately before a particular activity.

A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical

17. ________ activities are to be completed immediately following a particular activity.

A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical

18. The forward pass in project network calculations determines the

A. Earliest time's activities can begin
B. Earliest time's activities can be finished
C. Duration of the project
D. Both A and B are correct
E. A, B, and C are all correct

19. The backward pass in project network calculations determines the

A. Latest time's activities can begin
B. Earliest time's activities can be finished
C. Critical path
D. Both A and C are correct
E. A, B, and C are all correct

20. Which of the following correctly calculates the early finish for an activity?

A. LS + DUR
B. ES + DUR
C. LF + DUR
D. ES + SL
E. LF + SL

21. Which of the following correctly calculates the late start for an activity?

A. EF - DUR
B. ES - DUR
C. LF - DUR
D. ES - SL
E. LF - SLACK

22. The amount of time an activity can be delayed and yet not delay the project is termed

A. Total slack
B. Free slack
C. Critical float
D. Float pad
E. Slip pad

23. Which of the following will correctly calculate the total slack in an activity?

A. LS - ES
B. LF - EF
C. LS - LF
D. LF - ES
E. Both A and B are correct

24. The laying pipe example in the text illustrates the concept of

A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass

25. Using a special color copy machine for a tradeshow publication illustrates the concept of

A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass

26. If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

A. Check to see which activities cost the least
B. Check to see which activities have the longest duration
C. Check to see which activities are on the critical path
D. Check to see which activities have the most slack
E. Check to see which activities have the highest risk

27. Typically an activity on a project network represents

A. A single work package
B. One or more tasks from a work package
C. Several work packages
D. A sub-deliverable
E. A cost account

28. Project network logic errors include which of the following?

A. Activities with less than 1 day duration
B. Sequences such as "if test successful build prototype, if failure redesign"
C. A sequence such as B succeeds A, C succeeds B, A succeeds C
D. Both B and C are network logic errors
E. A, B, and C are all network logic errors

29. Which company utilized concurrent engineering to design a new line of cars and in the process completed its development six months ahead of schedule?

A. General Motors
B. Chrysler
C. Ford
D. Nissan
E. Toyota

30. The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:

A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer

Reference no: EM13928781

Questions Cloud

Probability of getting heads on at least one flip : You are to participate in an exam for which you had no chance to study, and for that reason cannot do anything but guess for each question (all questions being of the multiple choice type, so the chance of guessing the correct answer for each ques..
How much would you be willing to pay for one of the bonds : It is now January 2010, and interest rates have declined such that bonds of equivalent remaining maturity now sell to yield 11 percent. How much would you be willing to pay for one of these bonds today? Why?
Assessing materiality and risk : Resources: Assessing Materiality and Risk located on the Week Two Materials page Complete the simulation and prepare a 350-word total (not per question) response to the following questions:
What is the coupon rate and year of maturity for medtronic : What is the coupon rate and year of maturity for the Medtronic and Morgan Stanley bonds? How much would you have had to pay to buy one Anheuser Busch Inbev Worldwide bond at the closing trade?
Information to develop a project network : Information to develop a project network is collected from the  A. Organization breakdown structure B. Work breakdown structure C. Budget D. Project proposal E. Responsibility matrix
Different modes of foreign market entry : 1. A company has four different modes of foreign market entry. Which of the following WOULD NOT be among those modes?
Number of oil spills off the east coast discrete : 1. Decide whether the random variable is discrete or continuous.
Discuss importance of rfid to accounting information systems : Discuss the importance of RFID to accounting information systems:- Who uses it, and what are it's benefits?
Company uses activity : If the company uses activity-based costing (ABC), how much overhead cost should be assigned to Job 101

Reviews

Write a Review

Project Management Questions & Answers

  Explore the application of bim on safety planning

Virtual Design and Construction. Which project type would benefit more from employing VDC: New Construction or Re-development projects? Substantiate your answer by quoting real life cases, and examining the critical success factors for VDC.

  Detail the underlying reasons for the perceived failures

Critically analyze the case you have selected in order to detail the underlying reasons for the "perceived failures" in the project. Ensure that you make appropriate references to project management literature.

  Lowest ratio mixed assembly planning

Lowest Ratio Mixed Assembly Planning - For that mixture what is the lowest ratio mixed model assembly sequence

  Eac based on combined cost and schedule performance

Given EVM data, estimate the cost at completion of a project using the method "EAC based on Combined Cost and Schedule Performance.

  Need a paper on managing project resources

Need a paper on Managing project resources: time, cost, quality, risk, and scope

  Project management conflicts

How does it's organizational structure influence Project Management - Project management conflicts

  Q1a describe and compute the followingbull designed

q1a describe and compute the followingbull designed capacitybull effective capacitybull actual outputbull

  Company risks vs project risksboth eastman chemical company

company risks vs. project risksboth eastman chemical company a large natural gas user and van oil a major natural gas

  You understand why pmos fail and what you will do to

1.part 1 what are the basic principles behind the agile process?part 2 what is the pms role under the agile process?

  Factors driving force behind economic success

Explain why each of these factors is the driving force behind economic success.

  Facts and figures that are newly collected for a project

Facts and figures that are newly collected for a project at hand are called  Which of the following is not a criterion used in forming segments? Which of the following is a criterion used for selecting a target segment? Which of the following data ar..

  Individual as part of your project team

Would you want this individual as part of your project team and what will you do to get him? How should an organization cope with this situation?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd