Question: Given the following information about a small project,

Task    Duration        Immediate

           Estimates       Predecessors

A         2 days             None

B         5 days             A

C         1 day              B

D         2 days             A

E         3 days             B & D

F         12 days           E & C

  1. Draw a network diagram.
  2. Identify the critical path, earliest start and finishand slack for each task.
  3. Using MS Excel, produce a Gantt chart for this project.
  4. What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?

Reference no: EM132267635

Questions Cloud

Enterprise risk management program at mars incorporated : What represents the key success factors of the Enterprise Risk Management program at Mars Incorporated?
What is scope of a project : What headings are covered in that. Do we need to cover goals, deliverable, features, price and project task. What points are covered in each heading.
Compare and contrast stream and block ciphers : INFA640 - Cryptology and Data Protection - University of Maryland University College - Briefly compare and contrast stream and block ciphers
Continuing in a silo mentality : How do you succeed in making sure that the risk committee really turns into an ERM champion, as opposed to continuing in a silo mentality?
Information about a small project : Question: Given the following information about a small project,
Accomplished and the work environment : How does the project team match the work to be accomplished and the work environment?
Are normalized databases in general faster : Are normalized databases in general faster, slower, or exhibit about the same performance as non-normalized databases? Why?
Scope in management in project in healthcare : How important is the development of an effective Scope in Management in Project in Healthcare?
How can the pm circumvent the problem : How can the PM circumvent the problem that the monitoring system can only report on activities that have passed

Reviews

Write a Review

Project Management Questions & Answers

  Define a project and describe its characteristics

Define a project and describe its characteristics and What are the necessary competencies and skills of a project Manager?

  Determine the climate change effects on environment

BUSN20016 Identify the effects of co2 emission on Australian environment - Identify the effect of climate change occurred by co2

  Accounting project - financial analysis real life

accounting project - financial analysis real life decisionwe must come up with a real life financial situation and

  How did the release violate the adea

How did the release violate the ADEA?- Does the employer have a right to a setoff against this employee for the money paid to her by the employer?

  Create a simple communication plan for the execution

Create a simple communication plan for the execution of your creation of a coffee shop. This plan should have the following information: contact information for all affected parties

  Would chcs business performance be more exposed

Would CHC's business performance be more exposed to inflation in the United States as a whole or in the local area?

  Explore some of the other clustering procedures

Explore some of the other clustering procedures available in SAS, for example, proc modeclus, on the air pollution data.

  How does a project manager avoid culture shock

How does a project manager avoid culture shock? because culture shock is not a disease but a natural response to immersing yourself in a new environment.

  Purposes behind having a performance appraisal system

Which of the following reasons does NOT support the purposes behind having a performance appraisal system:

  Project baselinechanges during the life cycle of projects

project baselinechanges during the life cycle of projects are inevitable and will occur. some changes may be very

  Construct the complete pcm for the criterion location

John considers each kilometre of distance worth two units on the AHP value scale.- Construct the complete PCM for the criterion location.

  What kinds of data does it use to back up its argument

Is it an empirical report, a theoretical study, a sociological or political account, a case study?a historical overview etc.? What is its theoretical basis?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd