Reference no: EM133401736
Questions
1. In terms of project risk management methodology, prioritizing risks is critical because:
a. there is a limit to the number of risks all projects can have
b. all risks pose the same threat to project success
c. risk significance determines the allocation of time and energy we will spend in development of risk responses
d. projects usually have the same risks, regardless of complexity
2. Risk responses are:
a. proactive contingency plans that are established should the risks evolve into actual problems
b. historical ways to deal with risks in past projects only
c. always deployed in successful projects
d. a sign that a project is poorly managed
3. Select the appropriate treatment approach for the kind of risks that we are aware of and can manage:
a. the focus should be on effects and remediation
b. the focus should be on the individual who brought it to our attention
c. the focus should be on causes
d. the focus should be on the need for the requirement that encompasses that risk
4. In the terminology of project risk management, what's the best definition of a black swan event?
a. a high-profile, common event that may or may not slow the project down
b. an event similar to past events that keeps re-occurring
c. a high-impact, hard-to-predict, rare event
d. an event that must occur periodically in projects across industries
5. Unknown risks have no immediate treatment approach because we're not even aware that they exist.
True
False
Analysis of the internal and external environments
: Why should you ensure that your analysis of the internal and external environments is consistent with the perspectives of other informed people?
|
Discuss common ideas that can be found in both documents
: Discuss common ideas that can be found in both documents. Are the arguments similar or different? what concepts of natural rights appear in their arguments
|
What are the most common types of viruses
: Cybercrime and Cyber Terrorism by Robert W. Taylor-Chapter Viruses and Malicious Code: What are the most common types of viruses and why are they used today?
|
Develop an analysis, suggest recommendations
: Develop an analysis, suggest recommendations, and craft careful messaging that is sensitive to the crisis in Ohio, but once again brings awareness and feasible
|
In terms of project risk management methodology
: In terms of project risk management methodology, prioritizing risks is critical because. Risk responses are.
|
Do you think the jury made the right or wrong decision
: In the novel, To Kill a Mockingbird, we learned that Tom Robinson was found guilty of raping Mayella Ewell. Do you think the jury made right or wrong decision?
|
Different videos to illustrate different points
: demonstrate your careful viewing of each. Feel free to draw upon different videos to illustrate different points
|
How politics is exercised there
: How politics is exercised there; Main stages of its political evolution (eg birth, annexation, relations, conflicts, peace); Political accomplishments
|
What is an example of policy areas and tools
: What is an example of policy areas and tools that should be considered by decision makers as they develop their recovery plans?
|