Important information about pertcpm with optimistic most

Assignment Help Project Management
Reference no: EM13363224

Important information about PERT/CPM with optimistic, most likely, and pessimistic times

A project has the following activities, precedence relationships, and time estimates in days:

Activity Predecessor Optimistic Most likely Pessimistic
Activities Time Time Time
A -- 6 7 8
B A 4 4 4
C A 5 6 8
D B 8 10 10
E B 7 10 15
F C 9 9 13
G C 7 7 7
H D 4 6 8
I E, F 6 9 11
J G 8 9 10
K H, I, J 3 5 6

Compute the earliest start, earliest finish, latest start, latest finish, and slack for each activity

What are the critical path and duration of the project?

What is the probability that the project will take longer than 38 days?

Reference no: EM13363224

Questions Cloud

Calculating optimal production batch size1jims knives : calculating optimal production batch size1.jims knives manufactures knives for a certain retail store. his skilled
Project management contracting and procurementwhat kind of : project management contracting and procurementwhat kind of contract will you pursue for each of the following purchases
Concept of change management process in a projectexplain : concept of change management process in a projectexplain the concept of the change management process within a
Managing risks in project managementrisk is often described : managing risks in project managementrisk is often described as the event that might happen during the course of a
Important information about pertcpm with optimistic most : important information about pertcpm with optimistic most likely and pessimistic timesa project has the following
Project management for acme development corporation : project management for acme development corporation procurement processacme development corporation adc a developer of
The organizational culture of a firm may present a : the organizational culture of a firm may present a strategic opportunity for the firm. the organizational culture
Request for proposalswhat is an rfp and how do analysts use : request for proposalswhat is an rfp and how do analysts use one to gather information about hardware and system
Production manager alberto perez has been successful in his : production manager alberto perez has been successful in his u.s. assignment using a participative management style. if

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd