Question 1:

Consider the following table and answer the questions that follow

Activity

Description

Predecessor

Optimistic time in days

Most likely time In days

Pessimistic time in days

A

Position recruiting

 

5

8

17

8

System development

 

3

12

15

C

System training

A

4

7

10

D

Equipment training

A

5

8

23

 

Manual system test

B,C

1

1

1

F

Preliminary system change over

B,C

1

4

13

G

Computer personnel Interface

0,E

3

6

9

H

Equipment
modification

D,E

1

2.5

7

 

Equipment testing

H

1

1

1

System   debugging

and Installation

F,G

2

2

2

 

Equipment changeover

1,1

5

8

11

1.1 Determine the expected activity times

1.2 Develop an activity on arrow network diagram (ADA)

1.3 Determine the earliest start and finish times; and the latest start and finish time

1.4 Determine the critical path

1.5 Determine the expected project duration

Question 2

CASE STUDY: Project Charter; Payroll Project. Authorising the Project

This Charter formally authorizes the Payroll Project to develop and implement a new payroll system for use In Jones Consulting Company's payroll group. A project plan will be developed and submitted to the Project Sponsor for approval. The project plan will include: scope statement; schedule; cost estimate; budget; and provisions for scope, resource, schedule, communications, quality, risk, procurement, and stakeholder management as well as project control. All resources will be assigned by the Project Sponsor, Van Johnson, human Resources Director.

Project Scope

State the scope of the project, Its deliverable and what business needs, problems or opportunities the project addresses - a market demand, business need, legal requirement, social need, customer request or technological advance. The purpose of the Payroll project is to improve the timeliness and accuracy of payroll operations. This project meets Jones Consulting's need for improved efficiencies across all departments by reducing payroll cycle time and minimizing staffing required for payroll operations.

The project deliverables shall include: Payroll system design, all coding, testing and Implementation of an integrated system for use with existing IT Infrastructure and a user guides. The objectives of the Payroll project are: To reduce payroll cycle time by 30% and reduce payroll staffing by 20%. High level risks for this project include: Ensuring implementation is completed without impacting ongoing payroll operations and ensuring there are no issues with migrating payroll accounts from the legacy system to the new system. Success will be determined by the Project Sponsor once the system is implemented and one full payroll cycle has been completed that meets the objectives with no discrepancies.

The Project Manager

The Project Manager, Bill Smith, is hereby authorized to Interface with management as required, negotiate for resources, delegate responsibilities within the framework of the project, and to communicate with all contractors and management, as required, to ensure successful and timely completion of the project. The Project Manager is responsible for developing the project plan, monitoring the schedule, cost, and scope of the project during implementation, and maintaining control over the project by measuring performance and taking corrective action.

Milestones

The project plan will be submitted and approved In accordance with the milestone schedule below. Upon approval of the project plan resources will be assigned to the project and work will commence within 5 business days. The Project Sponsor must approve any schedule changes which may impact milestones. A detailed schedule will be included in the project plan. The high level milestone schedule is:

Feb 1, 2015 - Project Plan Complete and Approved

Mar 31, 2015 - Payroll Design Completed

May 31, 2015 Coding Completed

June 30, 2015 Testing Completed

July 31, 2015 - Beta Testing Completed

Sept 30, 2015 Implementation Completed

Oct 15, 2015 - One Payroll Cycle Complete and Project Completion

Question 3

3.1 Formulate at least five risks and associated Impacts based on your scope statement developed in question 2 above.

3.2 With motivation, score the risks on a quantitative risk assessment template.

3.3 Create a risk management plan for all the formulated risks

Reference no: EM13783833

Questions Cloud

Case - japan taxes on alcoholic beverages : Read the Japan Taxes on Alcoholic Beverages case. Pepare a case brief. Refer to the "How to Brief a Case" Web page when preparing your case brief
Create a windows application that functions like a banking : Create a Windows application that functions like a banking account register. Separate the business logic from the presentation layer (create a class with all the methods and properties).
Social services lobbyist within state legislature : Conduct an interview with a social services lobbyist within your State Legislature. Use the sameform of interview questions as in previous group interviews but include the following:
Use wertheims structure for case analysis : Write a formal case analysis (5-7 pages) of "The Virgin Group in 2012." Use Wertheim's structure for case analysis. Pay particular attention to the choices of corporate strategy when outlining the causes of any problems identified. Identify creative ..
Impacts based on your scope statement : Formulate at least five risks and associated Impacts based on your scope statement and score the risks on a quantitative risk assessment template.
Matt and grace should do before they talk with consultant : Matt and Grace own a small supermarket in a rural town with a large and growing elderly population. Because of their remote location, they don't have any competition from the large chain stores. A small private liberal arts college, with about 1,500 ..
Integrate the use of mediation : How does a human services worker integrate the use of mediation, or third-party neutrality, when he or she also serves as an advocate for the client and is an employee of the agency?
What is the cost benefit analysis for the rehabilitation of : What is the Cost Benefit Analysis for the Rehabilitation of the National Guard Armory in Massachusetts?
Case- shell v rw sturge ltd : For this assignment, you are to read the Shell v. R.W. Sturge Ltd. case and do the following: Prepare a case brief. Refer to the "How to Brief a Case" Web page when preparing your case brief

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd