Reference no: EM132266431
1. In CPM, for activities with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time:
a. largest EF among the immediate predecessors
b. smallest LF among the immediate predecessors
c. smallest EF among the immediate predecessors
d. average of EFs among the immediate predecessors
2. After defining a problem the next step in the problem solving/decision making process should be
A. Isstitute a temporary fix to keep things moving
B. Use five why analysis
C. Clearfy the issue or problem in order to grasp the situation
D. Define what the outcome should be
3. True or False: According to the textbook research reports that firms with 100 – 500 employees have approximately 7 decision-makers involved in the buying process.
4. True or False: According to the textbook 20% of your company’s future revenue will come from just 80% of your existing customers.
5.