Illustrate what is the probability that the project

Assignment Help Operation Management
Reference no: EM1377950

Q. A Project was planned utilizing PERT with three time estimates. The expected completion time of the project was found out to be 40 weeks. The variance of the critical path is 9.

(a) Illustrate what is the probability that the project will be finished in 40 weeks or less?

(b) Illustrate what is the probability that the project takes longer that the project takes longer than 40 weeks?

(c) Illustrate what is the probability that the project will be finished in 46 weeks or less?

(d) Illustrate what is the probability that the project will take longer than 46 weeks?

(e) The project manager wishes to set the due date for the completion of the project so that there is a 90% chance of finishing on schedule. Thus there would only be a 10% chance the project would take longer than this due date. Illustrate what should this due date be?

 

Reference no: EM1377950

Questions Cloud

Illustrate what is the logic in the least squares method : Illustrate what is the logic in the least squares method of linear regression analysis. Overall the logic of least squares method is used to forecast the next quarterly sales of the organization.
Explain how your organization could benefit from employing : Search the library also provide 2 research citations that illustrate examples of companies that are utilizing e-business strategies (e.g., B2B, B2C), also discuss explain how your organization could benefit from employing similar strategies.
Managerial training and development course : Determine what would you wish to include in a managerial training and development course for your mid level managers being transferred overseas? For foreign nationals coming to train in the United States?
Illustrate what quantities of h also w will maximize profit : There are 600 fabrication hours also 480 hours of assembly time available this week. Each H contributes $40 to profits; also each W contributes $30 to profits. Illustrate what quantities of H also W will maximize profits. Use the objective functio..
Illustrate what is the probability that the project : The expected completion time of the project was found out to be 40 weeks. The variance of the critical path is 9. Illustrate what is the probability that the project will be finished in 40 weeks or less.
Changing constraints to equalities : Change these constraints to equalities through adding the appropriate slack, surplus, or artificial variables. Also, add new variables into the problem's objective function.
Compare with flexible manufacturing system : Illustrate what are the problems in scheduling work in a assembly line production covering automatic batch manufacturing. Compare with flexible manufacturing system.
Find out optimal order size also the minimum total annual : The annual cost of carrying a pound of cheese in a refrigerated storage area is $12. Find out the optimal order size also the minimum total annual inventory.
Illustrate what is the realistic sales estimates : Illustrate what is the break-even point in dollars for all food sales. Illustrate what is the realistic sales estimates.

Reviews

Write a Review

Operation Management Questions & Answers

  Compute the single exponential smoothing forecast

Compute the single exponential smoothing forecast for this information using an ad of .30 and an initial forecast. Compute the mean absolute deviation (MAD) for each forecast.

  Given the volunteers you have the other time estimates item

Given the volunteers you have, the other time estimates are item K (2 hrs), item L (1 hour) also item M (4 hrs). Develop a time-phased assembly plan to prepare the gift bags.

  Elucidate how many immediate parents does item e have

Elucidate how many immediate parents (one level above) does item I have. Elucidate how many immediate parents does item E have. Elucidate how man unique components does product A have at all levels. Which of components are purchased items.

  Explain how would your remarks differ if group reserve

The rooms forecast committee is scheduled to meet later this afternoon. You have been asked to prepare remarks on group no-shows. Explain how would your remarks differ if the group reservation had been made.

  Describe b2b technologies also applications

Describe B2B technologies also applications also ways B2C can use technology to utilize e-business strategies.

  Explain how maintenance and housekeeping do in fact

Explain how maintenance and housekeeping do in fact help to accomplish main objectives of lean production-delivering value to customer through a flow system.

  Llustrate which three recent college graduates have opened

Three recent college graduates have opened an advertising industry. Illustrate what is the probability which the project will be completed in 24 days or less? 21 days or less

  Linear programming-maximize planting

A farmer in Lowa owns 45 acres of land. He is going to plant each acre with wheat or corn. It clearly indicates how the derived value has been reached.

  Risk identification and risk control

What is the difference between risk identification and risk control in the context of protecting information systems?

  Illustrate what is it about project management which offers

Illustrate what is it about project management which offers Mega tech a competitive advantage in its industry.

  Illustrate what is the theoretical number of workstations

Illustrate what is the theoretical number of workstations. Suppose that Demand rose from 750 to 1,000 units per day. Illustrate what would you do? Show any amount or calculations.

  Elucidate in words the number of gallons in the open tank

Suppose which instead of a faucet, a 60 gallon container is used for filling the tan. Elucidate in words the number of gallons in the open tank is changing over time also draw a graph of the situation

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd