Q. The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes. The accompany table shows the activities, time & sequence necessary:
Activity Immediate predecessor Time (weeks)A --- 3B A 2C A 4D A 4E B 6F C,D 6G D,F 2H D 3I E,G,H 3
A.) Illustrate what is the critical path?
B.) Assume you desire to shorten the completion time as much as possible, & you have the option of shortening any or all of B, C, D also G each one week. Which would you shorten?
C.) Illustrate what is the new critical path & earliest completion time?
Determine factors that should be evaluated when creating competitive strategy of a business. Indicate significance of each with supporting details.
Why is the idea of a ‘line of fit' such a useful concept in explaining describes how an operations strategy can be implemented successfully.
Assuming the addition of one or more clerk, illustrate what is the number of applications that the process can handle. Elucidate how would you suggest modifying the process in order to accumulate 120 applications per hour.
The data for the last week follows: Day # of Non-conformities 1 2 3 4 5 5 10 23 20 15 Construct a 3 standard deviation c chart of non-conformities. Elucidate what the control chart tells you about the IRS telephone operators
Could a service firm use a production-line approach or self-service design also still keep a high customer focus (personal attention). Explain also support your answer with examples.
Discuss the implications from an operations design viewpoint of such a change of business model also discuss also explain the types of operations (design) strategies also tactics.
Illustrate what would 3-sigma control limits for the process be. Illustrate what alpha risk would they provide.
explain whether investments in expatriate managers are worthwhile for such organizations.
Making a Critical Assessment of the Toyota Production System (TPS) Today Use of a Grid Analysis (Weighted Scoring Model) to Help Make the North American Plant Location Decision for the RX 330
Jane needs to try a more collaborative approach to working with suppliers. Will her approach work. Explain how should she adopt a more collaborative approach in future negotiations with suppliers.
Illustrate what factors must be considered in assessing legal sufficiency of an offer, acceptance and consideration in determining whether a contract is enforceable.
Grounded in your analysis also the identified problems, analyse also examine how the capabilities in B-A & H could be better cultivated. Use all four farms but emphasize the most relevant ones.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd