Q. A competitor of Kozar International, Inc. has begun marketing a new instant-developing film project. Kozar has had a similar product under study in its R&D department but has not yet been able to begin production. Because of competitor's action, top managers have asked for a speed up of R&D activities so that Kozar can produce and market instant film at earliest possible date. Predecessor information and activity time approximates in months are shown below.
Activity Immediate Predecessors Optimistic Time Most Probable Time Pessimistic Time
A - 1 1.5 5
B A 3 4 5
C A 1 2 3
D B,C 3.5 5 6.5
E B 4 5 12
F D,E 6.5 7.5 11.5
G F 5 9 13
a. Draw AOA project ne2rk.
b. For each activity, Compute mean and variance of activity duration time.
c. Using mean activity times conduct a CPM analysis and develop an activity schedule for this
Project using early and late start and finish times, compute activity slack time and define critical activities.
d. Illustrate what is expected (i.e. mean) project completion time? Standard deviation of completion time?
e. Illustrate what is probability project will be completed in time for Kozar to begin marketing new product within 24 months?
Illustrate what is average inventory if costs are minimized
: Illustrate what is average inventory if costs are minimized. Suppose that ordering cost is not $20.68 and Cotteler has been ordering 175 units each time an order is placed. For this order policy.
|
Discuss transportation and logistics management policy
: Discuss transportation and logistics management policy. Illustrate what impact does policy (local, state, and/or federal) have on transportation.
|
Illustrate what is flow time of process
: Illustrate what is possible daily output of this "process" if 8 hours of processing time is available each day. Given your output in part a, illustrate what is efficiency of process. Illustrate what is flow time of process.
|
Inter-temporal production possibilities
: Determine which of the following nations would you expect to have intertemporal production possibilities biased toward current consumption goods,
|
Illustrate what is probability project will be completed
: Illustrate what is expected (i.e. mean) project completion time. Standard deviation of completion time. Illustrate what is probability project will be completed in time for Kozar to begin marketing new product within 24 months.
|
About explain how many runs per year would there be
: About explain how many runs per year would there be. Explain how much could business save annually if setup cost could be reduced to $25 per run.
|
Comparative advantage for mexico
: During the debate over NAFTA, opponents argue that given the relative size of the two economies, the income gains resulting from the agreement would be smaller for the United States than for Mexico.
|
Should you take extra car
: Gross profit is $40 per car per day rented. When re is demand for a car when n1 is available re is a goodwill loss of $80 and rental is lost. Each day a car is unused costs you $5 per car. If your industry can obtain another car for $200 for 10 da..
|
Explain why did snop fall out favour with healthcare field
: Explain why did SNOP fall out of favour with healthcare field. Illustrate what are 4 approaches taken by HIM professionals to address complexities brought on by introduction of PPS and DRGs.
|