Q. A competitor of Kozar International, Inc. has begun marketing a new instant-developing film project. Kozar has had a similar product under study in its R&D department but has not yet been able to begin production. Because of competitor's action, top managers have asked for a speed up of R&D activities so that Kozar can produce and market instant film at earliest possible date. Predecessor information and activity time approximates in months are shown below.

Activity Immediate Predecessors Optimistic Time Most Probable Time Pessimistic Time
A - 1 1.5 5
B A 3 4 5
C A 1 2 3
D B,C 3.5 5 6.5
E B 4 5 12
F D,E 6.5 7.5 11.5
G F 5 9 13

a. Draw AOA project ne2rk.

b. For each activity, Compute mean and variance of activity duration time.

c. Using mean activity times conduct a CPM analysis and develop an activity schedule for this
Project using early and late start and finish times, compute activity slack time and define critical activities.

d. Illustrate what is expected (i.e. mean) project completion time? Standard deviation of completion time?

e. Illustrate what is probability project will be completed in time for Kozar to begin marketing new product within 24 months?

 

 

Reference no: EM1374961

Questions Cloud

Illustrate what is average inventory if costs are minimized : Illustrate what is average inventory if costs are minimized. Suppose that ordering cost is not $20.68 and Cotteler has been ordering 175 units each time an order is placed. For this order policy.
Discuss transportation and logistics management policy : Discuss transportation and logistics management policy. Illustrate what impact does policy (local, state, and/or federal) have on transportation.
Illustrate what is flow time of process : Illustrate what is possible daily output of this "process" if 8 hours of processing time is available each day. Given your output in part a, illustrate what is efficiency of process. Illustrate what is flow time of process.
Inter-temporal production possibilities : Determine which of the following nations would you expect to have intertemporal production possibilities biased toward current consumption goods,
Illustrate what is probability project will be completed : Illustrate what is expected (i.e. mean) project completion time. Standard deviation of completion time. Illustrate what is probability project will be completed in time for Kozar to begin marketing new product within 24 months.
About explain how many runs per year would there be : About explain how many runs per year would there be. Explain how much could business save annually if setup cost could be reduced to $25 per run.
Comparative advantage for mexico : During the debate over NAFTA, opponents argue that given the relative size of the two economies, the income gains resulting from the agreement would be smaller for the United States than for Mexico.
Should you take extra car : Gross profit is $40 per car per day rented. When re is demand for a car when n1 is available re is a goodwill loss of $80 and rental is lost. Each day a car is unused costs you $5 per car. If your industry can obtain another car for $200 for 10 da..
Explain why did snop fall out favour with healthcare field : Explain why did SNOP fall out of favour with healthcare field. Illustrate what are 4 approaches taken by HIM professionals to address complexities brought on by introduction of PPS and DRGs.

Reviews

Write a Review

Operation Management Questions & Answers

  Elucidate what kind of organization acme is

Managers at Acme Explosives supervise workers closely also use rewards also punishment to control their behaviour. Acme is a (n) Elucidate what kind of organization.

  Describe how you would analyze a process

Select one of the six steps for the blueprint for process analysis and describe how you would analyze a process. The process can be for school, work, home project etc.

  Determine annual cost of ordering and carrying cloth

A service garage uses 120 boxes of cleaning cloths per year. Boxes cost $6 each. Ordering cost is $3 and holding cost is 10 percent of purchase cost per unit on annual basis. Determine annual cost of ordering and carrying cloth.

  Solution to linear programming model

Frank Hurley is the farmer with 250 acres on which he wishes to plant wheat and corn to maximize his expected return for season. Based upon the output, what key points would you recommend to Frank?

  Explain how many kanbans card sets are needed

Due to variations in processing times due to the size and length of the bracelets, it has been decided to keep 25 percent of the needed inventory as safety stock. Explain how many kanbans card sets are needed.

  Draw charts and plot values of the sample means and ranges

Twelve samples, each containing 5 parts, were taken from a process that produces steel rods. The length of each rod in the samples was decided. Draw the charts and plot the values of the sample means and ranges.

  Describe demographic makeup

describe the demographic makeup in these years; then identify industries that will be impacted by these data.

  Do you think small businesses to compete in a global market

Do you think small businesses have any opportunity to compete in a global market. Explain how can they improve their success.

  Decide whether the supply chain represents a low-cost

Decide whether the supply chain represents a low-cost, rapid response or differentiation strategy. Are the supply-chain characteristics significantly different from one product to another.

  Operations versus supply chain management

This solution discussed the similarities and differences between operations and supply chain management. You have been asked to develop a short presentation on comparing and contrasting operations management to supply chain management.

  Create a report for your ceo which outlines the value

As the IT manager, you have been tasked with convincing your Corporation's CEO which the time has come purchase a new operating system also the latest office tools for the Corporation's computers. Create a report for your CEO which outlines the val..

  Evaluate your priority sequences

Evaluate your priority sequences in a) on average flow time from now, average lateness (with no credit for being early) and average days early (with zero days early for a job that is late).

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd