Identify the paths and path project durations

Assignment Help Project Management
Reference no: EM131162734

Table shows the precedence relationships among the activities to complete a project.

898_Precedence Relationship Table.jpg


a. Construct an activity on node network for the project.
b. Identify the paths and path project durations.
c. Determine the critical path and the expected project completion time.
d. Find the ES, LS, EF, LF, and slack time for each activity.

Reference no: EM131162734

Questions Cloud

Types of economic systems : State the defining characteristics of two types of economic systems: capitalism and socialism. How do these systems compare in terms of (a) overall productivity, (b) resulting economic inequality
Explain the assertion made in the text : Explain the assertion made in the text that race is socially constructed. That is, explain what biological traits may be used in defining race, but why a biological approach cannot explain the reality of race in the United States. Provide examples..
Prepare a cash budget for the month of july : Sushi House has budgeted sales revenues as follows: Credit sales: June $85,000, July $80,000, August $72,000. Cash sales: June $14,000, July $25,000, August $32,000. Prepare a cash budget for the month of July
What can an elderly grandma macionis teach : What can an elderly Grandma Macionis teach us about living a life that does not strain the natural environment? In what specific ways has life changed since her time? How have these changes affected the environment? What are the chances of regaini..
Identify the paths and path project durations : Identify the paths and path project durations. -  Determine the critical path and the expected project completion time.
Carla wahburn case : Refer to the Carla Wahburn case in the textbook's website (www.routledgesw.com/cases). Think about and discuss with your peers what fields of social practice may come into play in services to Ms. Washburn. Gerentology is obvious, but there are oth..
Personal values and beliefs regarding ethnic : Use the Journal to evaluate and identify your personal values and beliefs regarding ethnic groups and minorities. This self-evaluation should be written in paragraph form with an Introduction, Body, and Conclusion.
Find a 95% confidence interval for the coefficient of mangan : The data used to fit the model in Exercise 1 are presented in the following table, along with the residuals and the fitted values. Plot the residuals versus the fitted values. Does the plot indicate that the linear model is reasonable? Explain.
Criticism that modernization theory : There is much criticism that modernization theory is Eurocentric. Do you think dependency theory and globalization theory are also biased? Why or why not? Compare and contrast modernization theory, dependency theory, and globalization theory. Whic..

Reviews

Write a Review

Project Management Questions & Answers

  The important location factors and ratings

The important location factors and ratings

  Determining the other household costs

Victor gives his mother, Maria, $10,000 a year to help pay for her food, rent, and other household costs. Her only income is $8,000 in Social Security benefits.

  How might you apply the bpr process to an hrm office

How might you apply the BPR process to an HRM office that currently only has an employee database and no other automated HRM functions?

  Organizational environments

Organizational Environments - Most cross-cultural experts would identify the dominant acitivy orientation for Americans as

  Use as a project manager to improve the accuracy

Identify five common project risk strategies employed to address threats that your project may face. Give an example of each.

  Develop a risk assessment matrix for the briargrove project

Develop a risk assessment matrix for The Briargrove Project. Develop a Matrix for assessing an aspect of the project

  Difference between productive and counterproductive conflict

Show the differences between productive and counterproductive conflicts

  Draw a simple flow chart for processing changes

How should the project budget and expenditures be set out for cost control? Draw a simple flow chart for processing changes? How did EID handle their risks? Was this effective? What might they have done?

  Compute the total costs incurred in january

How many units were transferred from the Packaging Department to the Finished Goods Department during the month - what were the equivalent units of production for direct materials and conversion costs for the month of January?

  Project procurement and contract managementpurchasing

project procurement and contract managementpurchasing functionsintroductionin a large organization a specialized

  Was the sample size adequate

Was the sample size adequate?

  Time and cost constraints of project

How are they affected by change and Is there a triple constraint that is the most important? If so, which one and why?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd