Identify the critical path of the network

Assignment Help Project Management
Reference no: EM131555739

Quantitative Methods in Project Management

Problem 1: Given the information provided below (predecessors, normal time, normal cost, crash time (the minimum duration) and crash cost (the cost if crashed to the minimum duration) for an nine-activity (a to i) project) answer the questions (a) through (e) using this template.

Activity

Predecessor

Normal
Time

Normal
Cost

Crash
Time

Crash Cost

a

 

4

$50

2

$150

b

a

4

$40

2

$200

c

b

7

$70

4

$160

d

c, f

2

$20

1

$50

e

c

3

$30

2

$100

f

b

8

$80

5

$290

g

d, e

5

$50

3

$100

h

f

6

$60

 

$180

i

g, h

3

$50

3

$50

(a). Create the network diagram in the application of your choice and then insert a screen shot of the diagram here. The diagram can be created easily in MS Word using the Insert Shapes function.

Enter your network diagram in this space provided (you should delete this text box and use as much space as necessary to display your network diagram).

Identify the critical path of the network, the time, and cost of the normal level of activity for the project:

- The critical path (or paths) is:
- The project duration:

The project cost is:

(b). Calculate the crash cost-per-day (all activities may be partially crashed). Enter your response to question 1(b) in the table provided below

Activity

Normal
Time

Normal
Cost

Crash Time

Crash Cost

Crash
Cost/Day'

a

 

 

 

 

 

b

 

 

 

 

 

c

 

 

 

 

 

d

 

 

 

 

 

e

 

 

 

 

 

f          
g          
h          

(c). Find the optimal way to crash the project by one day.
- What is the projected project cost?
- What is the projected project duration?
- What is the critical path (or paths)?
- What task or tasks were crashed?
Explain the results of your calculations.

(d). Find the optimal way to crash the project by two days.
- What is the projected project cost?
- What is the projected project duration?
- What is the critical path (or paths)?
- What task or tasks were crashed?
Explain the results of your calculations.

(e). Calculate the shortest completion time for the project.
- What is the projected project cost?
- What is the projected project duration?
- What is the critical path (or paths)?
- What task or tasks were crashed?

Explain the results of your calculations.

Verified Expert

Please find the solution for session 9 for the problem related to quantitative methods provided . It is one simple method of critical path that are a part of quantitative methods used in project management.

Reference no: EM131555739

Questions Cloud

Discuss the impact of the various reimbursements : Discuss the impact of the various reimbursements (e.g., Medicare, Medicaid, private, or self-pay). Think about your upcoming capital proposal.
Classical techniques flourished under : What classical techniques flourished under early Christian patronage? Please use specific examples.
Examination of stereotypes and stereotype formation : Examination of stereotypes, stereotype formation,& the relationship of stereotypes to prejudice & discrimination is a field of study within social psychology.
What is the purpose of your chosen superpower : What is the purpose of your chosen superpower? How would this superpower allow you to accomplish your purpose as a superhero?
Identify the critical path of the network : Create the network diagram in the application of your choice and then insert a screen shot of the diagram here.
Describe two potential impacts of this type of prejudice : Describe two potential impacts of this type of prejudice on individual behavior or relationships when exhibited blatantly and exhibited subtly.
Write a paragraph that explains how to kick a bad habit : Write a paragraph that explains how to kick a bad habit. The paragraph should be an informational process analysis.
Develop complex topics with a rhetorical purpose : Develop complex topics with a rhetorical purpose. Deploy grammar and mechanics of standard written English. Use complex syntax and varied sentence structure.
Find a unit vector u in the same direction as v : Use the Gram-Schmidt process as in Example to produce an orthogonal basis for the column space.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd