Identify the critical path for the given activity

Assignment Help Data Structure & Algorithms
Reference no: EM131469574

Question: Consider Problem. Suppose that the normal and the expedited costs and times are as given in the following table.

1172_Act.png

If indirect costs amount to $100 per day, determine the optimal time to complete the project and the optimal project completion cost.

Problem: A project consists of seven activities. The precedence relationships are given in the following table.

1907_Act 1.png

a. Construct a network for this project.

b. Compute the earliest and the latest starting and finishing times for each activity and identify the critical path.

c. Draw a Gantt chart of the schedule for this project based on earliest starting times.

d. What group of activities will have to be completed by day 60 in order to guarantee that the project will not be delayed?

Reference no: EM131469574

Questions Cloud

Supply chain frameworks and organizations are relatively : Supply Chain frameworks and organizations are relatively new and continue to evolve.
Write up a psychological study : The purpose of a psychological lab report is to present an original research study to the scientific community - write up a psychological study
Which topic of conversation makes you uncomfortable : Which topic of conversation makes you uncomfortable? What is the topic? Do you know why you find it difficult to talk about this topic?
Demonstrate how knowledge processing tools can be used : You will expand on the key components identified in the first assignment through a relevant case study and gain a deeper knowledge of using strategic framework
Identify the critical path for the given activity : Consider Problem. Suppose that the normal and the expedited costs and times are as given in the following table.
List factor that nlrb considers to determine bargaining unit : List factors that NLRB considers to determine a bargaining unit. The ______ removed unions from Sherman Act jurisdiction and limited use of federal injunctions.
Filled out loan application and gave a super presentation : You took your nice business plan to the bank with a filled out loan application and gave a super presentation.
What can the hr department do to ensure its effectiveness : What does an organization need to do to ensure an effective HR department? What can the HR department do to ensure its effectiveness?
How much time is available for assembling final test gear : A guidance and detection system is being built as part of a large defense project. The detection portion consists of radar and sonar subsystems.

Reviews

Write a Review

Data Structure & Algorithms Questions & Answers

  Implement an open hash table

In this programming assignment you will implement an open hash table and compare the performance of four hash functions using various prime table sizes.

  Use a search tree to find the solution

Explain how will use a search tree to find the solution.

  How to access virtualised applications through unicore

How to access virtualised applications through UNICORE

  Recursive tree algorithms

Write a recursive function to determine if a binary tree is a binary search tree.

  Determine the mean salary as well as the number of salaries

Determine the mean salary as well as the number of salaries.

  Currency conversion development

Currency Conversion Development

  Cloud computing assignment

WSDL service that receives a request for a stock market quote and returns the quote

  Design a gui and implement tic tac toe game in java

Design a GUI and implement Tic Tac Toe game in java

  Recursive implementation of euclids algorithm

Write a recursive implementation of Euclid's algorithm for finding the greatest common divisor (GCD) of two integers

  Data structures for a single algorithm

Data structures for a single algorithm

  Write the selection sort algorithm

Write the selection sort algorithm

  Design of sample and hold amplifiers for 100 msps by using n

The report is divided into four main parts. The introduction about sample, hold amplifier and design, bootstrap switch design followed by simulation results.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd