Identify the critical path and the non critical activities

Assignment Help Project Management
Reference no: EM131305816

R.C. Coleman distributes a variety of food products that are sold through grocery store and supermarket outlets. The company receives orders directly from the individual outlets, with a typical order requesting the delivery of several cases of anywhere from 20 to 50 different products. Under the company's current warehouse operation, warehouse clerks dispatch orderpicking personnel to fill each order and have the goods moved to the warehouse shipping area. Because of the high labor costs and relatively low productivity of hand order-picking, management has decided to automate the warehouse operation by installing a computercontrolled order-picking system, along with a conveyor system for moving goods from storage to the warehouse shipping area. R.C Coleman's director of material management has been named the project manager in charge of the automated warehouse system.

After consulting with members of the engineering staff and warehouse management personnel, the director has compiled a list of activities associated with the project. The optimistic, most probable, and pessimistic times (in weeks) have also been provided for each activity. Activity Description Immediate Predecessor Optimistic time Most probable time Pessimistic time A Determine equipment needs ----- 5 6 7 B Obtain vendor proposals ----- 2 4 12 C Select vendor A, B 1 4 7 D Order system C 6 9 18 E Design new warehouse layout C 7 10 13 F Design warehouse E 3 5 7 G Design computer interface C 4 6 20 H Interface computer D, F, G 4 6 8 I Install system F 4 6 14 J Train system operators and test system H, I 3 5 7 The project manager asks you to analyze this project. You must write a managerial report, which should be turned in this afternoon by 4 p.m. The report should address the following issues:

a) Draw the project network

b) Develop an activity schedule

c) What is the expected completion time for this project?

d) Identify the critical path and the non-critical activities?

e) What are the chances of completing this project within the expected time computed in question c). Why? Justify your answer

f) R.C. Coleman's top management has established a required 35-week completion time for the project. Can this completion time be achieved? Include probability information in your discussion.

g) What are the chances of completing this project in 44 weeks or less? 48 weeks or less?

h) If the variance of the project completion time is the same (does not change) as you found previously, by how much time should the expected project completion time be shortened to achieve the goal of 80% chance of completion within 35 weeks?

Reference no: EM131305816

Questions Cloud

Effective way to an introductory sociology student : How do you think this relevance box could be revised to get its points across in a more effective way to an introductory sociology student? What shortcomings have you identified in the existing box and what ideas do you have for addressing them?  ..
What type information can concluded from forensic laboratory : what type information can be concluded from forensic laboratory examination(s) of the evidence. Any unique circumstances or problems relating to this type offense.
What are the short term effects of foreclosure in a region : What are the leading reasons for foreclosure in the states with the highest instances?What are the reasons for the low rate of foreclosure in the states with low occurrences?
Discuss rops and total costs : Martin-Pullin Bicycle Corp. (MPBC), located in Dallas, is a wholesale distributor of bicycles and bicycle parts. Formed in 1981 by cousins Ray Martin and Jim Pullin, the firm's primary retail outlets are located within a 400-mile radius of the distri..
Identify the critical path and the non critical activities : Draw the project network.- Develop an activity schedule.- Identify the critical path and the non-critical activities?
Analyze the documents and notate changes between them : Analyze the documents and notate changes between them. Identify the top three programs or services where funds are allocated on an annual basis.
The marketing concept holds : The marketing concept holds that ________.
Find the smallest value of k : a linear spring k is to be designed to stop a 20-mg railroad car traveling at 8km/h within 400 mm after impact. Find the smallest value of k that will produce the desired result.
What are the main weaknesses of the current system : What are the main weaknesses of the current system? What are the main strengths we want to maintain? How does the health system situation in Florida and / or US compare with that of other countries?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd