Assignment 1
1) Following are elements of a WBS for a project to build a bunk bed. Using the information supplied here, create a WBS and carry out a bottom-up cost estimate.
Cost($)
Rate ($/hr)
Time (hrs)
Research:
Jimmy' time
1
2
Dad's time
25
Materials:
Lumber 200
Hardware 45
Power equipment rental 65
Jimmy's time to acquire materials
3
Dad's Time to acquire materials
15
Construction:
Jimmy's time
8
20
Inspection:
Mom's time
10
0.5
2) Following is a listing of items to be considered in costing a PC game development project. Use this data to develop a parametric estimate of the cost of the project.
Cost ($) Rates($/hr) Time (hr)
Resources: Designers 30 100
Artists 25 200
Programmers 25 1000
Work Station 3000
Contracted Testing Group 50 100
Marketing Materials 1500
Fringe benefits: 30% of Direct Wages
Overhead: 70% of (Direct Wages + fringes)
3) For the table below
Task
Predecessor
Duration (in days)
Latest start
Earliest start
Float (slack)
A
Start
5
B
A,D
C
13
9
D
6
E
12
F
G
7
a) Create a PERT/CPM chartb) Identify the critical path and compute project durationc) Compute Latest Start, Earliest Start, and Float (Slack)
Verified Expert
The task file answered three problems related to project management. Work breakdown structure, project cost estimation and timeline were depicted in the answers. All three problems were resolved completely,
Fit a linear trend equation to the time series. Using this equation, determine the trend estimate for 2012.- Fit a quadratic equation to the time series, then use the equation to determine the trend estimate for 2012.
Describe the project that will be the basis for your final project - Create a Network diagram of the logical sequence of all activities and describe the tasks that you would need to complete in order to close out the project.
The scholarship is paid from a general scholarship fund and is awarded to students with high academic potential. Recipients are not required to perform any services to receive the scholarship.
When U.S. firms establish subsidiaries in foreign countries, management must determine the appropriate leadership style.
What a project is, how it functions, and how to structure a project for maximum efficiency and success, and you need to develop proficiency with MS Project
What is a full-service supplier firm? What type of services\ do they provide?- Describe limited-service supplier firms.
A person learns N items at a rate given.- Determine the total number of items learned in the first 12 hours of continuous study.
Describe how workplace policies or benefits could potentially support employees to balance their work and family responsibilities/needs.
What are the various delivery methods for training programs? List the steps in a seven-step methodology for implementing training?
What other dates would you expect the Educational Consultant to work on the project? Provide the WBS number and the dates in a table - Outline the possible risks and consequences
winsome manufacturing project scopeyou are a manager at winsome manufacturing company a company that produces plastic
How does the adoption of a particular methodology affect the researcher's choice of methods for data collection and analysis?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd