Identify the crashed network critical path

Assignment Help Project Management
Reference no: EM131035649

PERT Network Diagram 1 illustrates the ten interrelated activities that comprise a certain project.

PERT Network Diagram 1

The information presented in Table 1 represents the optimistic activity time (a), most probable activity time (m), and pessimistic activity time (b) in weeks for each activity associated with the project.

Table 1

Activity

Optimistic (a)

Most Probable (m)

Pessimistic (b)

A

2

3

4

B

1

3

5

C

2

5

8

D

4

10

16

E

2

4

6

F

3

6.25

8

G

2

4

6

H

1

3.25

4

I

1

2

3

J

3

5

7

PERT Network Diagram 2

1. Using the information provided in Table 1, calculate the expected activity time (t) in weeks for each activity and then enter this information in the appropriate data field provided for each activity in PERT Network Diagram 2 in order to complete this diagram. Use the Excel sheet provided by the Instructor.

2. Using the information provided in Table 1, calculate the variance for the estimated activity time for each activity.

3 - 14. Using the information in the completed PERT Network Diagram 2, calculate the overall estimated activity time in weeks for each possible of the 12 possible paths through the network. The following table may help you organize your data:

 

Question 3

P1 =

             

Question 4

P2 =

             

Question 5

P3 =

             

Question 6

P4 =

             

Question 7

P5 =

             

Question 8

P6 =

             

Question 9

P7 =

             

Question 10

P8 =

             

Question 11

P9 =

             

Question 12

P10 =

             

Question 13

P11 =

             

Question 14

P12 =

             

4. Identify the Critical Path.

5. Using the information provided in Table 1, and the critical path identified in the previous question, calculate the standard deviation for the project.

6. Using the information provided in Table 1 and completed Project Network Diagram 2 calculate the probability of the project critical path activities being completed in less than or equal to 36 weeks. (Assume a standard deviation of 2.50 weeks)

7. Using the information provided in Table 1 and completed Project Network Diagram 2 calculate the probability of the project critical path activities being completed in more than 41 weeks. (Assume a standard deviation of 2.50 weeks)

8. Using the information provided in Table 1 and completed Project Network Diagram 2 calculate the probability of the project critical path activities being completed between 37 and 42 weeks. (Assume a standard deviation of 2.50 weeks)

The information presented in Table 2 represents the calculated Earliest Start, Earliest Finish, Latest Start and Latest Finish times for each activity.

Table 2

Activity

Earliest Start

Earliest Finish

Latest Start

Latest Finish

A

0

3

0

3

B

3

6

3

6

C

6

11

11

16

D

6

16

6

16

E

16

20

18

22

F

16

22

16

22

G

22

26

22

26

H

22

25

23

26

I

26

28

26

28

J

28

33

28

33

9. Using the information provided in Table 2, calculate the slack time in weeks for each activity by filling out the PERT chart provided by the Instructor.

The information presented in Table 3 represents the total budgeted cost for each activity associated with the project.

Table 3

Activity

Total Budgeted Cost

A

$45,500

B

$38,750

C

$34,500

D

$13,750

E

$11,250

F

$10,900

G

$15,250

H

$14,750

I

$23,100

J

$15,650

10. Using the information provided in Table 2 and Table 3, calculate the budgeted costs at the end ofweek sevenof the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs at the end ofweek sevenof the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cash flow at the end ofweek sevenbetween these two scenarios. Use the Excel sheet provided by the Instructor. (10 points)

11. Using the information provided in Table 2 and Table 3, calculate the budgeted costs at the end ofweek elevenof the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs at the end ofweek elevenof the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cash flow at the end ofweek elevenbetween these two scenarios. Use the Excel sheet provided by the Instructor. (10 points)

Table 4 represents the percentage of completion and actual cost of work performed data for each activity associated with the projectat a certain point in timeduring the project.

Table 4

 

Activity

Total Budgeted Cost

Percent of Completion

Actual Cost of Work Completed

A

$45,500

100%

$46,750

B

$38,750

100%

$44,500

C

$34,500

100%

$33,250

D

$13,750

80%

$8,750

E

$11,250

70%

$8,800

F

$10,900

65%

$7,450

G

$15,250

30%

$4,850

H

$14,750

25%

$3,000

I

$23,100

0%

0%

J

$15,650

0%

0%

12. Using the information provided in Table 4, calculate the dollar value of work completed and the difference between Budgeted and Actual Cost for each activity. Which activity evidences the single largest activity difference (regardless of whether it is a cost overrun or cost under run) at this particular point in the project?

13. Using the information provided in Table 4 and the answer to the previous question, calculate the overall cost overrun or cost under run for the project at this particular point in the project.

Table 5 represents the estimated crash time in weeks and associated total crash cost for each activity.

Table 5

Activity

Crash Time

(Weeks)

Crash Cost

A

2

$52,500.00

B

2

$39,250.00

C

4

$36,000.00

D

9

$14,080.56

E

3

$12,250.00

F

2

$23,000.00

G

3

$18,500.00

H

2

$18,000.00

I

0

$30,000.00

J

1

$20,000.00

14. Using the information in the completed PERT Network Diagram 2 and Table 5, crash the network in order to reduce the estimated project duration to 31 weeks while minimizing the overall crash cost. Which critical path activity would be the most logical choice for thefirstactivity to crash?

15. Which of the following critical path activities would be the most logical choice for thesecondactivity to crash?

16. What is the total estimated cost associated with crashing the network to reduce the estimated project duration to 31 weeks at the lowest possible overall crash cost?

17. After successfully crashing the network to reduce the estimated project duration to 31 weeks, identify the crashed network critical path?

Reference no: EM131035649

Questions Cloud

The company break-even point : BREAK-EVEN ANALYSIS A company's fixed operating costs are $ 500,000, its variable costs are $3 00 per unit, and the product's sales price is $4 00. What is the company's break-even point; that is, at what unit sales volume will its income equal it..
Declared mentally incompetent by a court : Julian Makepeace, who had been declared mentally incompetent by a court, sold his diamond ring to Golding for value. Golding later sold the ring to Carmichael for value. Neither Golding nor Carmichael knew that Makepeace had been adjudged mentally in..
Find the optimal contract for the two types of workers : Find the optimal contract for the two types of workers in the full information setting. Now consider the hidden information setting.  Write the low-productivity worker's participation constraint and the high-productivity worker's incentive compatib..
Description of the problems-uml diagrams : The main components that should be included in the report are brief description of the problems, the UML diagrams, and your approach to solving the problems. In the report, you should explain the data fields used, the classes, and the methods alo..
Identify the crashed network critical path : Using the information in the completed PERT Network Diagram 2 and Table 5, crash the network in order to reduce the estimated project duration to 31 weeks while minimizing the overall crash cost. Which critical path activity would be the most logi..
Entered into an agreement with ups supply chain solutions : Ethicon, Inc., a pharmaceutical company, entered into an agreement with UPS Supply Chain Solutions, Inc., to transport pharmaceuticals. Under a contract with UPS’s subsidiary, Worldwide Dedicated Services, Inc., International Management Services Co. ..
Speculate on the planning mechanism : Per the text, planning isn’t just what you do to go into business; it’s what you have to do to stay in business. Speculate on the planning mechanism(s) that you believe would work well for your business if implemented properly. Provide a rationale fo..
How should marketing strategy differ across these products : Name two product categories for which the brand is generally selected first and the outlet second, two for which the reverse is true, and two for which these decisions are generally made simultaneously. Justify your selections. How should marketing s..
Optimal capital structure carlisle industries : OPTIMAL CAPITAL STRUCTURE Carlisle Industries is trying to determine its optimal capital structure, which now consists of only common equity. The firm will add debt to its capital structure if it minimizes its WACC, but the firm has no plans to us..

Reviews

Write a Review

Project Management Questions & Answers

  Detail the characteristics the lead

Projects in the News REFLECT on the APA Exposed Tutorial in the Lecture Folder for this week. Review any newspaper article, periodical, or journal - printed oronlinethat has been published within the last three (3) months that is project-related.

  Situational factors that influence team development

Analyze the development of the team in terms of the four-phase model. Does this model describe how the team evolved and analyze the group in terms of situational factors that influence team development.

  Project deliver the benefits-results as promised

Did the project deliver the benefits/results promised?

  In what ways can utility affect the market

What is utility? In what ways can utility affect the market and your response should be at least 200 words in length.

  Explain common processes utilized for project selection

Explain Common processes utilized for project selection and evaluation Common to Contemporary Organizations like NPV, ROI, PBP

  Details regarding salary and withholdings

Kimberly Cerny is a graduate student. She is 22 years old and works part-time as a grad- uate assistant in the biology department. In the summer, Kimberly was an intern at Neutrobio, Inc. Details regarding her salary and withholdings from her empl..

  Show the primary duties of the termination manager

Explain the various ways a project may be terminated and show the primary duties of the termination manager?

  Explain the process of subdivision of activities

Explain the process of subdivision of activities and events that composes the tree diagram known as the Work Breakdown Structure.

  Characteristics of a high-performance project team

What would you consider the attributes of high-performing project teams and what issues do you think most prevent teams from becoming high-performing and what would you do to address those issues?

  Workload on the development team

which group requires the most work by the project manager, and which group puts a higher workload on the development team. Provide a rational for your response.

  Techniques estimating time and cost in projects

Discuss the techniques that companies are using today for estimating time and cost in their projects.

  Reducing project durationcritical path and critical project

reducing project durationcritical path and critical project requirements could indeed be separate issues. this is why

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd