Identify the advantages to outsourcing project work

Assignment Help Management Theories
Reference no: EM131465260

1. The Procurement Management Plan although part of the PMP would start to be developed in which stage of the project life cycle?

A. Initiation

B. Planning

C. Executing

D. Monitor & Control

2. Disadvantages of outsourcing project work may include all of these except:

A. increased conflict

B. coordination breakdowns

C. increased costs

D. loss of control

3. Which of the following are valid contract types?

A. Build, Own, Operate, Transfer (BOOT)

B. Build, Own, Operate (BOO)

C. Build, Operate, Transfer (BOT).

D. All the given answers are correct.

4. Which of these is not a valid cost reimbursable contract type?

A. Cost plus flexible fee (CPFF) contracts

B. Cost plus incentive fee (CPIF) contracts

C. Cost plus award fee (CPAF) contracts

D. Cost plus fixed fee (CPFF) contracts

5. The driving motive for increasing the use of outsourcing on projects is:

A. reducing the trade deficit

B. reducing costs

C. improving international sales

D. making products more international in design

6. Recent outsourcing trends have shown an increasing emphasis on the suppliers for all of these except:

A. further cost reductions

B. increased quality of work performed

C. increased ability to collaborate

D. increased ability to work together

7. Which of these is not a key to successful partnering relationships?

A. Mutual trust

B. Jointly shared risk

C. Total company involvement

D. Independent project teams

8. Best practices in outsourcing project work include all of these except:

A. training and teambuilding activities

B. well established conflict management processes

C. frequent reviews and status updates

D. All the given answers are correct.

9. Best practices in outsourcing project work include all of these except:

A. training and teambuilding activities

B. well established conflict management processes

C. frequent reviews and status updates

D. All the given answers are correct.

10. To avoid problems with schedules and deadlines you should:

A. develop detailed schedules

B. hold frequent status reviews

C. add a penalty clause to the contract

D. hold frequent conversations with the outsourcer

11. How is risk shared in partnerships?

A. One party only

B. 50/50

C. With the new partnership entity

D. All the given answers are correct.

12. Which of these is not one of the key points of principled negotiation?

A. Use objective criteria when possible

B. Be honest and forthright

C. Focus on interests, not positions

D. Invent options for mutual gain

13. Which is not one of the six stages of contract negotiation?

A. Offer and acceptance (agreement)

B. Intention to create legal relations

C. Engagement

D. Consideration

14. Which of these is not one of the elements of good negotiation?

A. Conflict on a project can be good

B. Negotiation is not a contest

C. Seek first to understand, then to be understood

D. All the given answers are correct.

15. Which of the following is reflected in the saying ‘Seek first to understand, then to be understood'?

A. Separate people from the problem

B. Be honest

C. Focus on interests, not positions

D. Invent options for mutual gain

16. A project manager should adopt the preferred suppliers of the parent organisation.

True False

17. A firm fixed price contract offers the buyer less risk than the seller?

True False

18. The cost plus fixed fee (CPFF) contract is where a fixed fee is agreed upon for an estimated amount of work (determined during project estimating). This fee, together with agreed ‘allowable costs', are subsequently billed back to the supplier.

True False

19. Dispute arrangements should be agreed but not documented in the contract?

True False

20. Sub-contracting arrangements should be agreed and documented in the contract?

True False

21. In partnering, access to each other's organisation resources is available.

True False

22. It is a good idea to add a penalty clause to an outsourcing agreement because deadlines are often taken as a suggestion rather than a commitment.

True False

23. List 12 contract/tender selection criteria that would be vital to consider in any contaract/tender selection.

24. Describe the key activities carried out in the Initiation stage of the project life cycle from a procurement perspective.

25. Describe the key activities carried out in the Planning stage of the project life cycle from a procurement perspective.

26. Describe the key activities carried out in the Execution stage of the project life cycle from a procurement perspective.

27. Describe the key activities carried out in the Closing stage of the project life cycle from a procurement perspective.

28. Identify the four advantages to outsourcing project work.

29. Identify the disadvantages of outsourcing project work.

Reference no: EM131465260

Questions Cloud

What are the six major activities implementing project close : How does the project manager meet the challenge of keeping the project team focused on the remaining project activities and delivery to the customer until the project is complete?
What is hrs ethical duty : What is HR's ethical duty? Explain why this may fall under corporate responsibility and insider trading.
Develop the plates eom in the horizontal direction : Figure illustrates a plate with mass m = 2000 kg that is supported by four identical columns that are cantilevered from the ground.
Examine the renaissance baroque and romanticism movements : Examine the following five movements Renaissance, Baroque, Romanticism, Impressionism and Modernism. The name and time period of the movement.
Identify the advantages to outsourcing project work : Describe the key activities carried out in the Closing stage of the project life cycle from a procurement perspective-Identify the four advantages.
Company manufactures product consisting of three components : ABC company manufactures a product consisting of three components. The company manufactures the first and second components but supplies the third component fro
Determine the plates natural frequency : Figure shows a plate with mass m = 2000 kg that is supported by four identical columns that are cantilevered from the ground. Each column has length l = 2 m.
Company assembles and then tests two models of drones : A company assembles and then tests two models of drones, aerial and land-based. company wants to decide how many of each model to assemble and then test.
How should you decide whether to sell the product : what are the steps you would employ in reaching your decision? How does the theory of ethics that is applied affect your answer?

Reviews

Write a Review

Management Theories Questions & Answers

  Learning in action

Learning contract proposal that will form the basis of your learning contract report.

  Change is the only constant

"Change is the only constant " Evaluate the different types of change that have occurred in Sony.

  How do advertisers try to use group influence

How do advertisers try to use group influence?  Will you find any specific examples and explain the relevant theory of group behavior and influence?

  Case study:saving sony

You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.

  How the stock market works

The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.

  Find the optimal production quantities

Find not only the optimal production quantities, but also the optimal total cost.

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  Case study : bert''s bonsai and aquatic sport museum

Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.

  Knowledge management techniques

Demonstrate understanding of the many-sided nature of knowledge management

  Theory of transtheoretical model

Demonstrate understanding of the many-sided nature of knowledge management

  Write a paper on historical trends of management

Write a paper on Historical Trends of Management.

  Theory of reasoned action

Theory of Planned Behavior and Integrated Behaviors Model

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd