Identify critical path activities and as a project manager

Assignment Help Project Management
Reference no: EM133402744

Task: you are required to read the New Hockey Arena Project case study. Given the information provided in the case study, construct a network schedule for the project using MS Project and answer the case study questions.

Scenario The city has announced a new XYZ project and is sending a request for quotation to receive bids. ABC Corporation is developing a bid for the project, which is a 20,000 seats tennis stadium. The start date for the project is 28 July 2020. The area must be ready by 10 Apr 2021. A penalty clause of $5,000 per day for delay beyond Feb. 15th, 2022 is included in the contract. Given the information provided in the table below, answer the case study questions.

ID Activity Duration Predecessors 1 Hockey Arena 2 Clear site 20 3 Demolish the existing structures 25 2 4 Prepare construction site 20 3 5 Piling 90 4 6 Pour lower concrete 80 5 7 Pour main concourse 70 6 8 Install playing field 60 6 9 Construct upper steel bowl 90 6 10 Install seats 80 9 11 Build luxury boxes 70 days 9 12 Install jumbotron 18 days 9 13 Stadium infrastructure 95 9 14 Construct steel canopy 50 10 15 Light installation 25 days 10 16 Build roof supports 80 days 4 17 Construct roof 95 days 16 18 Install roof tracks 70 days 14 19 Install roof 60 days 17,18 20 Inspection 27 days 8,11,13,15, 19 Table 1: Technical details for the XYZ Project that must be addressed in planning

assume the following: A. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

B. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.

C. The construction crew work Monday through Friday.

Case Study Questions

1. As a project manager, you are aware that you must focus on your critical path to mitigate the risk of delay. Identify your critical path activities and as a project manager, describe your plan to ensure critical path receives the attention it deserves.

Provide a detailed explanation of the above question with reference sites

Reference no: EM133402744

Questions Cloud

Community for the multi-agency coordination : What are the processes in your community for the multi-agency coordination of local, state, and federal resources?
How do you analyze total landed cost for purchasing : How do you analyze total landed cost for purchasing a truck? Give examples for 4 cost items
Why are speeches and essays different : Why are speeches and essays different? As speakers we should strive to write for the what? Listeners go back and forth among what three actions?
Technological clockspeed and capital availability : Key strategic sourcing criteria for determining whether functions should be outsourced are: Technological clockspeed, Capital Availability
Identify critical path activities and as a project manager : Identify your critical path activities and as a project manager, describe your plan to ensure critical path receives the attention it deserves
Equipment, and training for the above project : An RFP is being developed and will be sent to vendors for the supply of technical services, equipment, and training for the above project
Why did europeans assume african indigenous missionaries : Why did Europeans assume that African indigenous missionaries could be more successful in spreading Christianity than Europeans themselves.
Apply the pillow method to an interpersonal issue : Apply the Pillow Method to an interpersonal issue that has recently affected you. Describe your thoughts and feelings at each position on the pillow
Operations management activities : Explain how you will successfully implement the 10 Critical Operations Management activities - specifying details, with examples for every point.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd