Identify and recommend types that may be most appropriate

Assignment Help Project Management
Reference no: EM133564304

Case Study: We were doing a mooring system project for an offshore oil rig in the Gulf of Mexico. It was a fixed price contract, but the specifications were sprinkled with a lot of TBDs (to be determined) items. As the project manager, the TBDs required a lot of attention and caused tremendous headaches between the customer's project manager and myself. I had to watch theseTBDs like a hawk. When a TBD specification was finalized by the customer, I had to ensure that the clarified specification was doable and that it did not affect my project's cost and time constraints.

Out of a dozen TBD specifications, one was for the smoothness of a stainless steel surface. I had to negotiate this TBD specification rigorously with the customer's project manager. I did not want to accept a tight specification that would have required extra fine machining of stainless steel surfaces of our system. We first agreed on the smoothness measurement technique and then the measurement sampling location and measurement length for traces.

Then we agreed on the maximum Ra value, maximum value of the arithmetic average of absolute values of vertical deviations of the roughness profile from the mean line. I sent my customer's project manager an e-mail outlining the agreed upon smoothness specification in detail and asked him to send me his approval note for this TBD specification. After I received his approval note, I initiated an engineering change order for the project specifications in our document control system. I distributed the final smoothness specification to all the engineers and manufacturing people who were involved with the stainless steel surfaces. I also sent a copy of the released project specification to my customer's project manager.

One by one, we negotiated and agreed on all the TBD specifications. One of these specifications was the interface drawings that were supposed to be delivered to us after four weeks from the start of the project. It took them six weeks to deliver the interface drawings to us. We were lucky to receive them in six weeks and fortunately, they did not affect the progress of my project. So I did not raise any ruckus with my customer about this crucial delay. I kept their delay as an ace in my pocket to exchange it with a future project delay that could have happened on our side. We finished all our stress calculations and system component designs on time. We as a team were ready for the mooring system design review.

We had a two-day meeting at our facilities. During the meeting, the customer's chief engineer told us that the slots that were designed into the mooring system were good for the chain passage, but they were not sized appropriately for the passage of the chain connectors. My team and I were quite surprised by this announcement by our customer because the project specifications clearly identified the chain size and dimensions and also identified that there would be no chain connectors in this mooring system. I showed them their specifications. My customer's team was embarrassed to realize their slip in project specifications.

My customer's project manager emphasized that we had to redesign the mooring system for the chain connector passage. The only solution was to evaluate the impact of this major change to our project on manpower, cost, and schedule. I asked my customer's project manager to give me two days to analyze the effects of this major change and to provide him with a written revised proposal. He accepted my offer and they left our facilities after throwing a major twist into the project. We had to redo all of our stress calculations and change our design drawings. On top of it all, I was not even sure if all the designers on my team were available for the expanding project. I had a meeting with my team to get their time estimates for the customer's new change order. I estimated the time and cost impact of the engineering change order on the project. I met
with the managers of each member of my team regarding their availability for the extended project.

After I had all the facts, I collected my upper management team for a meeting and showed them the impact of our customer's change order. They made some minor changes to my cost estimates. I got the upper management's blessing for the change order. Then I wrote a formal response to my customer's project manager for their proposed change. The project was delayed by two months and this major slip in my customer's specifications cost them 20% extra. My customer's project manager discussed my schedule and cost impact on the project to their change order with his upper management. They had no negotiation leverage but to accept my proposal. The surprising change order was a major slip on their part. My team finished the project two weeks earlier than promised. My team's efforts to finish the project two weeks early received excellent reviews from my customer's project manager.

QUESTION: The case study project was riddled with uncertainties of the project costs. Appraise the various types of contracts. Identify and recommend the types that may be most appropriate for the case study project and ensure that you justify your choice.

 

Reference no: EM133564304

Questions Cloud

Identify new knowledge the group member shared : Identify new knowledge the group member shared that you had not considered. Describe how this new knowledge identified by your peer could impact your nursing
Discusses the economic concept known as opportunity costs : The book discusses the economic concept known as opportunity costs. Please post a reflection on the opportunity costs you face for taking this class.
How might rates of uninsured persons impact the rates of hiv : How might rates of uninsured persons impact the rates of HIV diagnosis, deaths, and prevalence (how does no insurance status at the population level influence,
Share the mechanism of action of the medication and hints : Share the mechanism of action of this medication and hints for monitoring, side effects, and drug interactions of which one should be aware.
Identify and recommend types that may be most appropriate : Identify and recommend the types that may be most appropriate for the case study project and ensure that you justify your choice.
Prepare a report that defines and explains colonoscopy : Prepare a report that defines and explains Colonoscopy procedure as it relates to the patient preparation, expectations and reasons for the test
What are your thoughts on what hospitals and physicians can : What are your thoughts on what hospitals and physicians can do to succeed in the value-based environment?
Difference between independent and dependent demand : Discuss the difference between independent and dependent demand. Explain with a practical example.
What does the transition from volume to value mean : What does the transition from Volume to Value mean in health care? Explain and provide an example. Does this transition mean that volume is no longer

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd