Case Study: Hunter Engineering Group

In the beginning

Hunter Engineering was established in 1936 and is now a public limited company in which the Hunter family owned the controlling interest. It relied solely on Government Contracts as primary source of business. Until the late 1990s, contracts had been placed on a "cost plus" basis, but with the government's shift in policy towards reductions in public expenditure, the method of placing contracts had been changed to "fixed price". Sizes of the contracts were reduced. Instead of relying solely on large contracts involving over a hundred employees or more for up to 5 years, the company handled contracts that frequently involved less than 15 employees for a duration of under two years. Having projects at the right staffing levels and efficiency drives meant that between 1998 and 2012, employee levels had fallen from 1,500 to 720. Staffing levels in the Electrical Engineering Department fell from 45 to 26 over the same period. Between 2012 and 2017, further organisational restructuring initiatives resulted in the loss of over 170 employees.

Peter Green, Project Manager in Electrical Engineering, had joined the company in 1987 as a relatively young senior electrical engineer in his early 30s, and for the first ten years of his employment at Hunter Engineering, he worked on just 2 very large projects, each spanning 5 years. He had not enjoyed this long-term project commitment, so was relieved to find himself transferred to smaller projects because of more projects with lower staff levels. After working on 16 smaller projects in various capacities, first as the Project Team Leader, and later as a full Project Manager, he was promoted to Small Projects Director in January 2017. His promotion coincided with the company's decision to rename itself Hunter Engineering Group, a signal that it intended to diversify going forward.

Going commercial

January 2018, Peter put forward his ideas to expand the Electrical Department by going commercial and tendering for contracts outside the Government Defense Portfolio. While this had received the agreement of his Divisional Head, Peter was well aware of the problems facing smaller commercial projects in a company, where operations had to be defined solely by government interests and requirements.

The company had very high fixed overheads, but more importantly the highly demanding Quality Assurance System, a mandatory for government defense work meant rigid processes that included time-consuming Government contracts. For example, every deviation from the issued drawing had to be recorded and approved with a dated electronic signature from the Head of the Design Unit. Thus, any scope for judgement was not permitted by the inspection engineers. Peter realised that one of his first problems was to introduce some scope for judgement if small commercial projects were to be viable.

Hunter Engineering Group had no experience in tendering for commercial projects. Government contracts required very strict and complex approval process, which include documentation with contributions from all departments. It would therefore require considerable effort on Peter's part to prevent these departments from getting in the way when it came to new commercial ventures, particularly as most departments were looking for work - due to the downturn in recent government projects.

Peter was also concerned about staffing levels. The Electrical Engineering Department's involvement in minor projects could be anything from 3 months to 2 years in duration. Yet extra staff could only be recruited if it could be shown that there would still be a shortage in twelve months' time. The Electrical Engineering Department was always 25 percent understaffed due to difficulties involved in the forward planning of the workload. Recruitment policy remained unchanged. Peter estimated a need for 6 more engineers. Staff morale was falling. New graduates that joined required training. The senior engineers in the department were having to spend more and more time training the new graduates. Although there was a dearth of experienced engineers between the 25 to 40 age group, these qualified engineers found higher paying positions outside Hunter Engineering. While new graduates saw their 20-year age gap between themselves and their seniors and felt that promotion was impossible, so they left at the earliest possible moment.

The Sales Operations Team was also a serious cause for concern for Peter. It was staffed by ex-government employees who responded to general staff requirements issued by the Government Department. They sold only components and products which the company had already manufactured and approved by the government regulators. They did not explore the market to assess its future needs, nor did they initiate any internal research and development activity.

A further problem arose in the Manufacturing Department. The continuity of large projects meant that the staff employed at the end of one fiscal year would be employed only at the start of next year. The Finance Department therefore had become accustomed to delaying the issue of engineering and manufacturing order numbers by up to 6 weeks into the new fiscal year.

The HR Department moved slowly. Several weeks could elapse between an interview and the issue of an offer of employment. They seemed unconcerned that experienced engineers were at a premium and that new graduates steadily left Hunter after two years, thus continuing to exacerbate the age gap. Peter's current engineering staff on small commercial projects numbered 4 where 3 were new graduates with less than 6 months' professional experience, and one was an engineer with merely five years' experience.

As such Peter is determined to get more work into the department and to increase staff levels in order to handle it. He is particularly determined to initiate action change. His priority was to write a change proposal to the Senior Executive Team, via his Divisional Head. He needs change and he developed a change plan to the Electrical Department by going commercial.

Questions

1. What economic, political and culture issues are raised? Justify your answer with evidence from the case.

2. What are the relevant change concepts, theories, and frameworks that can be applied to this case? Provide at least two and justify the relevance of each theory.

3. Outline a change plan demonstrating how Peter preferred strategy or strategies could be put forward to address the issues and problems in this case. Provide a brief outline of each strategy and a timeline for the execution of Peter's proposed implementation plan. Don't forget to include evaluation and maintenance actions in Peter's plan.

 

Reference no: EM133312600

Questions Cloud

What kind of activity is daniel engaged in : Daniel has been known to spend an hour each morning sitting in front of his computer researching potential customers. What kind of activity is Daniel engaged in
Identify a relevant narrowed-down historical topic : Identify a relevant narrowed-down historical topic related to military modernization in Western societies, and explain why the issue is significant
What made hamers speech particularly powerful : Why was the president so concerned? (Explain the historical context.) What made Hamer's speech particularly powerful
How does vr affect many aspect of institutions : How does VR affect many aspect of institutions and practical aspects or in companies in supply chain management .with in text citiation apa7 please "from google
Hunter engineering group : What are the relevant change concepts, theories, and frameworks that can be applied to this case?
Different uses of history that du bois explain : What are these two different uses of history that Du Bois explains? Read the following passage from W.E.B. Du Bois's final chapter of his 1935 book
Why do nonunion companies seek to avoid unionization : Why do nonunion companies typically seek to avoid unionization? How do nonunion companies go about trying to avoid unionization?
What did the europeans think of these strange : What did the Europeans think of these strange, exotic foods, and what impact has this fascination had on global eatibg habits?
How is the incorporation of the labor movement : How is the incorporation of the labor movement into politics in Mexico, Brazil, and Argentina different?  What fueled the rise of revolutionary ideas in Latin

Reviews

Write a Review

Business Management Questions & Answers

  How many different types of customer

How many different types of customer may there be for a systems development project? Who are they?

  Pros and cons of open salary policy

A) What are the pros and cons of open salary policy?

  Discuss the trend in the inflation rates

a. Discuss the trend in the inflation rates between the U.S. and European countries during this period.

  Outline three practical social distancing strategies

Outline three practical social distancing strategies / recommendations relating to different elements of event management including aspects

  Stage four of the conflict process

Thinking back to Stage Four of the conflict process, discuss one of the types of intentions with which Pauline might struggle in this situation

  What are the factors from your perspective that foster

What are the factors from your perspective that foster the building of higher purpose/ethical organizations? Be sure to explain your reasoning.

  Calculate jacob total sales

Calculate Jacob's total sales for this month and last month as well as the variances and percentage variances in each of his revenue categories then answer

  Industry and competitive environment

What are the seven questions we ask when we assess the company's industry and competitive environment?

  Different types of economic system

In this paper you also have to imagine that you are the owner of a company and could select one of the different types of economic system.

  Compute the mean-median-range-and standard deviation

Compute the mean, median, range, and the standard deviation for the time it took to service each type of client

  Question on annual interest rate

3. Use Goal Seek to determine the "Annual Interest Rate" that would be required if the PMT is $500.

  Why do contracts include incentives

Why do contracts include incentives? When is it best to use an incentive? How are contracts used to transfer risk?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd