DELAY CLAIMS

Review this case care/ ully and answer the questions at the end of the case in detail. You are the contracting officer in charge of administration of a contract for the manufacture of aircraft jet engines. The contract was entered into on August 18, l 9XO, for a firm-fixed-price and contains the normal general provisions. The delivery schedule on this contract must be adhered to since the engines are to be furnished to aircraft manufacturers as government -furnished property.

During the performance of this contract the following delays occur:

1. September 10 to October 18, 19XO - on September 10, the contractor informed you that the specifications for the jet engine contained a number of requirements which could not be met if the delivery schedule was to be met. Your review of the specific requirements pointed out by the contractor indicates that they are primarily items that were added to the specification after the last procurement by your technical division.

Your technical people review the items and agree that most of them can be changed back to the previous requirements in order to facilitate meeting the schedule. Your change order accomplishing this reaches the contractor on October 18. In the interim, the contractor has been working on the manufacturing engineering aspect of the contract but has been unable to order long lead time components. He claims 30 days delay.

2. October 12-26, 19XO - a strike of the machinists in the contractor 's plant closes the plant completely.

3. November 3 to December 21, 19XO - on November 3, your technical division informs you that a major change to the rotor section of the engine must be processed since defects have been reported in the field. You order the contractor to conduct an immediate expedited study of this problem under his continuing engineering contract (a separate contract) and to submit a proposed design change in three weeks. Because of the urgency of this redesign your technical people spend the three weeks at the contractor's plant and are able to process the change in 10 days after it is submitted by the contractor. You issue the change on December 7, and the contractor takes two additional weeks to process the change through manufacturing engineering into his plant. He stopped work on the rotor assemblies on November 3, when he found out about the change and therefore claims a delay of the entire 48 days.

4. January 5 to February 7, l 9Xl - on January 5, the Excello Company informed the contractor that they were unable to deliver the subcontracted fuel pump for the engine because they cannot hold the precise tolerances required to manufacture the pump. In previous contracts the contractor had bought these pumps from the Ace Pump Company with no difficulty. However, on this procurement , following the clause in the contract requiring competition in subcontracting to the maximum practical degree, the contractor had awarded the job to Excello on the basis of their low competitive bid. The contractor immediately awarded another contract to Ace with orders to expedite delivery to the maximum. He claims a delay of 33 days.

Facing a delivery schedule calling for initial deliveries on April 15, 19Xl , and knowing that the government would not allow schedule slippage, the contractor began working overtime on December 1, 19XO. As further slippages occurred, he added extra shifts and took all possible steps to expedite progress on the contract. However, it was apparent that he was in trouble and on January 25, 19X1, the head of your agency called a meeting with the contractor to determine what could be done. At this meeting the head of your agency told the contractor that the contract must be performed on schedule and suggested that he take further steps to assure timely delivery.

The contractor worked Saturdays and Sundays from that time on and was able to deliver the initial group of engines at the end of April 19Xl (two weeks late). He now claims compensation for the overtime, shift premmm, loss of efficiency m expediting, subcontractor expediting costs, etc.

QUESTIONS:

How would you handle such a claim? Discuss each of the claimed delays and claim for additional compensation.

Verified Expert

The task pertains to answering the questions based on the given case study. The intention while answering the questions is to complete the project on time so that government time restraints can be respected. The charges can also be deducted if the project is not completed on time. Therefore, keeping everything in mind, the questions have been best answered being the in charge of the project being undertaken.

Reference no: EM131689303

Questions Cloud

Features of the emerging global security environment : How would you describe the key features of the emerging global security environment of the 21st century?
Create your own computer crime scene investigation sop : Create your own Computer Crime Scene Investigation Standard Operating Procedures (SOP). Assume that you are the Program Manager of a new company.
Discuss the importance of separation of duties : Discuss the importance of Separation of Duties, how it's implemented and why in some cases difficult to accomplish.
Differentiate probability and nonprobability sampling : Under what circumstances does the sampling distribution of the proportion approximately follow the normal distribution?
How would you handle such a claim : How would you handle such a claim? Discuss each of the claimed delays and claim for additional compensation - urnished to aircraft manufacturers as government
Technical aspects of a random number generator : Discuss the technical aspects of a Random Number generator and Pseudo-Random Number generator to include their appropriate applications
Discuss important in influencing behavior for this culture : you believe to be very important in influencing behavior for this culture in each of the lifespan stages
Operating system software to function : Because routers and switches are computing devices they both rely on operating system software to function.
Difference between a stratified sample and a cluster sample : What are some potential problems with using fishbowl methods to select a simple random sample? What is the difference between a stratified sample and a cluster.

Reviews

inf1689303

2/20/2018 5:34:35 AM

I received my paper, and it is truly awesome. I'm exceptionally satisfied with it. I do get it. I apologize for sending the numerous distraught and furious messages and voice messages the previous evening and early today. I was happy to the point that you called me early today and guaranteed me it would be rectified. Much obliged to you. All turned out well, the paper has been explored and now submitted to my educator 5 hours before the due time, and I can rest simple today evening time :) Thanks again

Write a Review

Supply Chain Management Questions & Answers

  Firms supply management function to strategic status

What types of managerial decisions in foreign countries are driven by cultural factors? What are some cultural factors that U.S. companies must recognize when doing business in Latin America? Why are many organizations using a hybrid approach to deci..

  Explain what metrics should be used to assess

Identify some of the logistics activities that the business engages in and explain what metrics should be used to assess how effective the logistics function is that would be important to customers.

  True of convenience sampling-example of curbstoning

The difference between probability sampling and nonprobability sampling is that in nonprobability sampling: Which of the following is true of convenience sampling? Which of the following is an example of curbstoning?

  Fair prices to the men and women

How much value does the agent or distributor add to a bouquet of flowers or bunch of roses from Africa before it reaches the final consumers? How can this be accurately calculated to ensure fair prices to the men and women who work on flower farms..

  What is the maximum capacity of the heat treat operation

A furnace used in the heat treat operation of cast iron railroad car couplers can hold up to 20 parts. The operation takes an average of 4 hours to process a batch of parts with a standard deviation of 2 hours. What is the maximum capacity (parts per..

  Briefly describe the supply chain or warehouse

Briefly describe the supply chain or warehouse and then carry out a pareto analysis on the inventory holding and present the results.

  What are the major sources of uncertainty that affect supply

What are the major sources of uncertainty that can affect global supply chain decisions. Consider the financial, logistic, political, natural, cultural, and technological sources of uncertainty in your response.

  Spectrum of the helium atom

How does the spectrum of the hydrogen atom differ from the spectrum of the helium atom?

  Discuss three software applications that you have utilized

Discuss three software applications that you have utilized in a K-12, higher education or business setting. Determine the purpose for the software being used for this setting.

  Disclose the potential risk of cancellation to investors

Would a person who adheres to the principle of rights consider it ethical for Stilton not to disclose the potential risk of cancellation to investors?

  Identity the supply chain process of anti retro virus drugs

Identity the supply chain process of anti retro virus drugs by NACO of GOVT OF INDIA With its comparable to planning framework and enables with four different head

  What is the difference between human and social capital

Supply chain managers should be concerned about three flows in their organizations. What are these three flows, and why are they important?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd