A two-workstation cell uses a kanban system to produce 400,000 parts per year. Expected leadtime to replenish a container is 0.75 hours (i.e. 45 minutes). Parts cost $60 and have an inventory opportunity cost of 20%. There are three material handling options available:
Manual - annual fixed cost of $25,000, cost per trip = $0.15, Max load size = 2;
Push Cart - annual fixed cost of $25,000 + $5,000 initial investment (amortized over 3 years), cost per trip = $0.25, Max load size = 20; and
Forklift - annual fixed cost of $25,000 + $75,000 initial investment (amortized over 6 years), cost per trip = $0.50, Max load size = 500.
Note: The company uses a MARR of 10% for all investments.
Workstation 1 has an external setup of 0.45 hours and a unit processing time of 0.05 hours. Workstation 2 has an external setup of 0.70 hours and a unit processing time of 0.04 hours.
a) Specify the following system design parameters: container size, material handling type, # kanban that will be feasible and minimize material handling cost.
b) Given that there are significant setups, how many kanbans will be necessary to authorize a production run? What will be the utilization of each workstation?
c) How would the system be different if it was controlled by CONWIP versus Kanban?
|
Calculate the magnitude of the torque applied to the bat
: Calculate the magnitude of the torque applied to the bat, assuming conservation of energy.
|
|
How kinetic energy is transferred to potential energy
: Discuss giving examples and relevant calculations with equations, how kinetic energy is transferred to potential energy or vice versa.
|
|
How fast will the sled be moving when it reaches reach
: How fast will the sled be moving when it reaches reach the other end of the field?
|
|
Calculate the expected return on the stock
: The beta for exposure to market risk is 1, and the beta for exposure to commodity prices is also 1. What is the expected return on the stock?
|
|
How would the system be different if it was controlled
: Given that there are significant setups, how many kanbans will be necessary to authorize a production run? What will be the utilization of each workstation?
|
|
How is an object moving before the centripetal force is acti
: How is an object moving before the centripetal force is acting on it? What is the shape of the path of motion, velocity, and force issues?
|
|
What is the focal length of the mirror
: A 1 cm tall bulb is placed in front of the mirror such that its image is formed 10 cm in front of the mirror.
|
|
What is the cost of common equity capital for the firm
: If the current price of Two-Stage's common stock is $14.60, what is the cost of common equity capital for the firm?
|
|
Determine the capitalized cost for each design
: Design B is more sophisticated, including computer controls; it has an initial cost of $5,975,000, has annual operating and maintenance costs of $550,000.
|